To determine: The standard time for the operation
Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.

Answer to Problem 22P
Thestandard time is calculated as 10.12 minutes.
Explanation of Solution
Given information:
The allowance factor is given as 10%. The observed time and performance rating for each element is given as follows:
Element | Performance rating | Observation (minutes per cycle) | ||||
1 | 2 | 3 | 4 | 5 | ||
Check mini-bar | 100 | 1.5 | 1.6 | 1.4 | 1.5 | 1.5 |
Make one bed | 90 | 2.3 | 2.5 | 2.1 | 2.2 | 2.4 |
Vacuum floor | 120 | 1.7 | 1.9 | 1.9 | 1.4 | 1.6 |
Clean bath | 100 | 3.5 | 3.6 | 3.6 | 3.6 | 3.2 |
Formulae to calculate the standard time:
Calculate the standard time:
Element | Performance rating | Observation (minutes per cycle) | Average time | Normal time | ||||
1 | 2 | 3 | 4 | 5 | ||||
Check mini-bar | 100% | 1.5 | 1.6 | 1.4 | 1.5 | 1.5 | 1.5 | 1.5 |
Make one bed | 90% | 2.3 | 2.5 | 2.1 | 2.2 | 2.4 | 2.3 | 2.07 |
Vacuum floor | 120% | 1.7 | 1.9 | 1.9 | 1.4 | 1.6 | 1.7 | 2.04 |
Clean bath | 100% | 3.5 | 3.6 | 3.6 | 3.6 | 3.2 | 3.5 | 3.5 |
Total | 9.11 |
Excel worksheet:
Calculate the average time to check mini-bar:
The average time is calculated by taking an average of the observation given, which is a summation of 1.5, 1.6, 1.4, 1.5, and 1.5 and dividing the result by 5. Hence, the average is 1.5 minutes.
Calculate the average time to make one bed:
The average time is calculated by taking an average of the observation given, which is summation of 2.3, 2.5, 2.1, 2.2, and 2.4 and dividing the result by 5. Hence, the average is 2.3 minutes.
Calculate the average time to vacuum floor:
The average time is calculated by taking an average of the observation given, which is summation of 1.7, 1.9, 1.9, 1.4, and 1.6 and dividing the result by 5. Hence, the average is 1.7 minutes.
Calculate the average time to clean bath:
The normal average time is calculated by taking an average of the observation given, which is summation of 3.5, 3.6, 3.6, 3.6, and 3.2 and dividing the result by 5. Hence, the average is 3.5 minutes.
Calculate the normal time to check mini-bar:
The normal time is calculated by multiplying average time and performance rating. The average time is given as 1.5 minutes, and performance rating is given as 100%. Hence, the normal time is 1.5 minutes.
Calculate the normal time to make one bed:
The normal time is calculated by multiplying average time and performance rating. The average time is given as 2.3 minutes, and performance rating is given as 90%. Hence, the normal time is 2.07 minutes.
Calculate the normal time to vacuum floor:
The normal time is calculated by multiplying average time and performance rating. The average time is given as 1.7 minutes, and performance rating is given as 120%. Hence, the normal time is 2.04 minutes.
Calculate the normal time to clean bath:
The normal time is calculated by multiplying average time and performance rating. The average time is given as 3.5 minutes, and performance rating is given as 100%. Hence, the normal time is 3.5 minutes.
Calculate the total normal time:
The normal time is calculate by adding the normal time to check the mini-bar, make one bed, vacuum floor, and clean bath.
Hence, the total normal time is 9.11 minutes.
Calculate the standard time:
The standard time is calculated by dividing the normal time with the value attained by subtracting the allowance factor from 1. Normal time is calculated as 9.11 minutes and the allowance factor is calculated as 0.10 or 10%.
Hence, the standard time is 10.12 minutes.
Want to see more full solutions like this?
Chapter 10 Solutions
Principles Of Operations Management
- Hyundai Motors is considering three sites-A, B, and C-at which to locate a factory to build its new electric car batteries. The goal is to locate at a minimum-cost site, where cost is measured by the annual fixed plus variable costs of production. Hyundai Motors has gathered the following data: Site Annualized Fixed Cost Variable Cost per Battery Produced A $11,000,000 $2,600 B C $2,000 $1,100 $20,000,000 $25,000,000 The firm knows it will produce between 0 and 60,000 batteries at the new plant each year, but, thus far, that is the extent of its knowledge about production plans. a) The value of volume, V, of production above which site C is recommended = batteries (round your response up to the next whole number).arrow_forwardHyundai Motors is considering three sites-A, B, and C-at which to locate a factory to build its new electric car batteries. The goal is to locate at a minimum-cost site, where cost is measured by the annual fixed plus variable costs of production. Hyundai Motors has gathered the following data: Site Annualized Fixed Cost Variable Cost per Battery Produced A $11,000,000 $2,500 B C $2,100 $1,050 $20,000,000 $25,000,000 The firm knows it will produce between 0 and 60,000 batteries at the new plant each year, but, thus far, that is the extent of its knowledge about production plans. a) The value of volume, V, of production above which site C is recommended = batteries (round your response up to the next whole number).arrow_forwardThe importance of keeping track of invoices and budgeting in a nursing home kitchen and how can a nutritionist utilize this in their career? Please not just a short explanation.arrow_forward
- The importance of interviewing potential food service aides and how can a nutritionist utilize this in their career? Please not just a short explanation.arrow_forwardWhat role does job analysis and job evaluation play in the compensation decision? Give an example of an organization NO AIarrow_forwardI did the first half correct! Please help me with the second half, not quite sure of the naive approach. Thanks in advance!arrow_forward
- Because my tutor and I didnt get it rightarrow_forwardOperations Managementarrow_forwardHow does wellness reflect and impact the past and the future of our health as a workout routine? What are the obstacles during the workout routine, and how do you overcome the obstacles? What are the best solutions to plan and accomplish the wellness?arrow_forward
- My last question! Thank you all for helping me better understand how OM works. If you can assist me for this one I'd be very thankful. Can you explain it step by step?I know now that LS is late start, and ES is early start. - •Activities on the critical path are? •The total project completion time for Rafay Ishfaq's software firm is how many weeks?•Determine the slack time for each of the activities for A-F •What is the total slack for the non critical paths in Rafays project?arrow_forwardThank you so much! I was able to answer C without help! Can you assist me with slack time for A-F? I believe A=0arrow_forwardThere's 8 parts, but I need some help with them. I always get confused on which is most critical of a patharrow_forward
- Understanding Management (MindTap Course List)ManagementISBN:9781305502215Author:Richard L. Daft, Dorothy MarcicPublisher:Cengage LearningManagement, Loose-Leaf VersionManagementISBN:9781305969308Author:Richard L. DaftPublisher:South-Western College Pub
- Foundations of Business - Standalone book (MindTa...MarketingISBN:9781285193946Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningFoundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning