Principles Of Operations Management
Principles Of Operations Management
11th Edition
ISBN: 9780135173930
Author: RENDER, Barry, HEIZER, Jay, Munson, Chuck
Publisher: Pearson,
Question
Book Icon
Chapter 10, Problem 22P
Summary Introduction

To determine: The standard time for the operation

Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.

Expert Solution & Answer
Check Mark

Answer to Problem 22P

Thestandard time is calculated as 10.12 minutes.

Explanation of Solution

Given information:

The allowance factor is given as 10%. The observed time and performance rating for each element is given as follows:

Element Performance rating Observation (minutes per cycle)
1 2 3 4 5
Check mini-bar 100 1.5 1.6 1.4 1.5 1.5
Make one bed 90 2.3 2.5 2.1 2.2 2.4
Vacuum floor 120 1.7 1.9 1.9 1.4 1.6
Clean bath 100 3.5 3.6 3.6 3.6 3.2

Formulae to calculate the standard time:

Average time=Observed times for gift-wrappingn

Normal time=Average time×Performance rating

Standard time=Normal time1Allowance factor

Calculate the standard time:

Element Performance rating Observation (minutes per cycle) Average time Normal time
1 2 3 4 5
Check mini-bar 100% 1.5 1.6 1.4 1.5 1.5 1.5 1.5
Make one bed 90% 2.3 2.5 2.1 2.2 2.4 2.3 2.07
Vacuum floor 120% 1.7 1.9 1.9 1.4 1.6 1.7 2.04
Clean bath 100% 3.5 3.6 3.6 3.6 3.2 3.5 3.5
Total 9.11

Excel worksheet:

Principles Of Operations Management, Chapter 10, Problem 22P

Calculate the average time to check mini-bar:

The average time is calculated by taking an average of the observation given, which is a summation of 1.5, 1.6, 1.4, 1.5, and 1.5 and dividing the result by 5. Hence, the average is 1.5 minutes.

Average time=Observationn=1.5+1.6+1.4+1.5+1.55=7.55=1.5 minutes

Calculate the average time to make one bed:

The average time is calculated by taking an average of the observation given, which is summation of 2.3, 2.5, 2.1, 2.2, and 2.4 and dividing the result by 5. Hence, the average is 2.3 minutes.

Average time=Observationn=2.3+2.5+2.1+2.2+2.45=11.55=2.3 minutes

Calculate the average time to vacuum floor:

The average time is calculated by taking an average of the observation given, which is summation of 1.7, 1.9, 1.9, 1.4, and 1.6 and dividing the result by 5. Hence, the average is 1.7 minutes.

Average time=Observationn=1.7+1.9+1.9+1.4+1.65=8.55=1.7 minutes

Calculate the average time to clean bath:

The normal average time is calculated by taking an average of the observation given, which is summation of 3.5, 3.6, 3.6, 3.6, and 3.2 and dividing the result by 5. Hence, the average is 3.5 minutes.

Average time=Observationn=3.5+3.6+3.6+3.6+3.25=17.55=3.5 minutes

Calculate the normal time to check mini-bar:

The normal time is calculated by multiplying average time and performance rating. The average time is given as 1.5 minutes, and performance rating is given as 100%. Hence, the normal time is 1.5 minutes.

Normal time=Average time×Performance rating=1.5×100%=1.5×1=1.5 minutes

Calculate the normal time to make one bed:

The normal time is calculated by multiplying average time and performance rating. The average time is given as 2.3 minutes, and performance rating is given as 90%. Hence, the normal time is 2.07 minutes.

Normal time=Average time×Performance rating=2.3×90%=2.3×0.9=2.07 minutes

Calculate the normal time to vacuum floor:

The normal time is calculated by multiplying average time and performance rating. The average time is given as 1.7 minutes, and performance rating is given as 120%. Hence, the normal time is 2.04 minutes.

Normal time=Average time×Performance rating=1.7×120%=1.7×1.2=2.04 minutes

Calculate the normal time to clean bath:

The normal time is calculated by multiplying average time and performance rating. The average time is given as 3.5 minutes, and performance rating is given as 100%. Hence, the normal time is 3.5 minutes.

Normal time=Average time×Performance rating=3.5×100%=3.5×1=3.5 minutes

Calculate the total normal time:

The normal time is calculate by adding the normal time to check the mini-bar, make one bed, vacuum floor, and clean bath.

Normal time=Sum of normal times=1.5+2.07+2.04+3.5=9.11 minutes

Hence, the total normal time is 9.11 minutes.

Calculate the standard time:

The standard time is calculated by dividing the normal time with the value attained by subtracting the allowance factor from 1. Normal time is calculated as 9.11 minutes and the allowance factor is calculated as 0.10 or 10%.

Standard time=Normal time1Allowance factor=9.11 minutes10.10=9.11 minutes0.9=10.12 minutes

Hence, the standard time is 10.12 minutes.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
At the Ford automobile Highland plant, assume the one-millionth vehicle was produced in 1916 at a cost of $8084 (in 2013 US$), by how much did the Ford company reduce his cost with each doubling of cumulative output from 1916 to 1927?
At the Ford automobile Highland plant,in 1913, how long did the average worker stay with the plant and what was the average tenure of a worker?
Community Federal Bank in Dothan, Alabama, recently increased its fees to customers who use employees as tellers. Management is interested in whether its new tee policy has increased the number of customers now using its automatic teller machines to that point that more machines are required. The following table provides the number of automatic teller transactions by week. Use trend projection with regression to forecast usage for weeks 13-16.
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
Foundations of Business (MindTap Course List)
Marketing
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Foundations of Business - Standalone book (MindTa...
Marketing
ISBN:9781285193946
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning