a)
To determine: The normal time for the operation
Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.
a)

Answer to Problem 25P
Thenormal time calculated as 3.23 minutes.
Explanation of Solution
Given information:
The allowance for tasks is given as 7% for personal, 10% for fatigue, and 3% for delay. The observed time and performance rating for each element is given as follows:
Element | Performance rating | Observation (minutes per cycle) | ||||
1 | 2 | 3 | 4 | 5 | ||
1 | 110% | 0.5 | 0.4 | 0.6 | 0.4 | 0.4 |
2 | 95% | 0.6 | 0.8 | 0.7 | 0.6 | 0.7 |
3 | 90% | 0.6 | 0.4 | 0.7 | 0.5 | 0.5 |
4 | 85% | 1.5 | 1.8 | 2 | 1.7 | 1.5 |
Formulae to calculate normal time:
Calculate the normal time:
Element | Performance rating | Observation (minutes) | Average time | Normal time | ||||
1 | 2 | 3 | 4 | 5 | ||||
1 | 110% | 0.5 | 0.4 | 0.6 | 0.4 | 0.4 | 0.46 | 0.51 |
2 | 95% | 0.6 | 0.8 | 0.7 | 0.6 | 0.7 | 0.68 | 0.65 |
3 | 90% | 0.6 | 0.4 | 0.7 | 0.5 | 0.5 | 0.54 | 0.49 |
4 | 85% | 1.5 | 1.8 | 2 | 1.7 | 1.5 | 1.7 | 1.45 |
Excel worksheet:
Calculate the average time for the first element:
The average time is calculated by taking an average of the observation given, which is summation of 0.5, 0.4, 0.6, 0.4, and 0.4 and dividing the result by 5. Hence, the average is 0.46 minutes.
Calculate the average time for the second element:
The average time is calculated by taking an average of the observation given, which is summation of 0.6, 0.8, 0.7, 0.6, and 0.7 and dividing the result by 5. Hence, the average is 0.68 minutes.
Calculate the average time for the third element:
The average time is calculated by taking an average of the observation given, which is summation of 0.6, 0.4, 0.7 0.5, and 0.5 and dividing the result by 5. Hence, the average is 0.54 minutes.
Calculate the average time for the fourth element:
The average time is calculated by taking an average of the observation given, which is summation of 1.5, 1.8, 2.0, 1.7, and 1.5 and dividing the result by 5. Hence, the average is 1.7 minutes.
Calculate the normal time for the first element:
The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 0.46 minutes, and performance rating is given as 110%. Hence, the normal time is 0.51 minutes.
Calculate the normal time for the second element:
The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 0.68 minutes, and performance rating is given as 95%. Hence, the normal time is 0.65 minutes.
Calculate the normal time for the third element:
The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 0.54 minutes, and performance rating is given as 90%. Hence, the normal time is 0.49 minutes.
Calculate the normal time for the fourth element:
The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 1.7 minutes, and performance rating is given as 85%. Hence, the normal time is 1.45 minutes.
Calculate the total normal time:
The normal time is calculated by adding the normal time of all the elements.
Hence, the total normal time is 3.08 minutes.
b)
To determine: The standard time for the operation.
Introduction: Time study is the basis that helps set the standard time, it would time a sample of the performance of the worker.
b)

Answer to Problem 25P
Thestandard time is calculated as 5.4 minutes.
Explanation of Solution
Given information:
The allowance for tasks is given as 7% for personal, 10% for fatigue, and 3% for delay. The observed time and performance rating for each element are given as follows:
Element | Performance rating | Observation (minutes per cycle) | ||||
1 | 2 | 3 | 4 | 5 | ||
1 | 110% | 0.5 | 0.4 | 0.6 | 0.4 | 0.4 |
2 | 95% | 0.6 | 0.8 | 0.7 | 0.6 | 0.7 |
3 | 90% | 0.6 | 0.4 | 0.7 | 0.5 | 0.5 |
4 | 85% | 1.5 | 1.8 | 2 | 1.7 | 1.5 |
Formulae to calculate standard time:
Calculate the allowance factor:
The allowance factor is calculated by adding personal allowance, fatigue, and delay allowance. Personal allowance is given as 7%, fatigue is 10%, and delay allowance is 3%. Hence, the allowance factor is 20%.
Calculate the standard time:
The standard time is calculated by dividing the normal time with the value attained by subtracting the allowance factor from 1. The normal time is calculated as 3.08 minutes and the allowance factor is calculated as 20%
Hence, the standard time is 3.85 minutes.
Want to see more full solutions like this?
Chapter 10 Solutions
Principles Of Operations Management
- Define risk management and explain its importance in a small business.arrow_forward1. Define risk management and explain its importance in a small business. 2. Describe three types of risks commonly faced by entrepreneurs. 3. Explain the purpose of a risk register. 4. List and briefly describe four risk response strategies. (5 marks) (6 marks) (4 marks) (8 marks) 5. Explain how social media can pose a risk to small businesses. (5 marks) 6. Identify and describe any four hazard-based risks. (8 marks) 7. Mention four early warning indicators that a business may be at risk. (4 marks)arrow_forwardState whether each of the following statements is TRUE or FALSE. 1. Risk management involves identifying, analysing, and mitigating risks. 2. Hazard risks include interest rate fluctuations. 3. Entrepreneurs should avoid all forms of risks. 4. SWOT analysis is a tool for risk identification. 5. Scenario building helps visualise risk responses. 6. Risk appetite defines how much risk an organisation is willing to accept. 7. Diversification is a risk reduction strategy. 8. A risk management framework must align with business goals. 9. Political risk is only relevant in unstable countries. 10. All risks can be eliminated through insurance.arrow_forward
- 9. A hazard-based risk includes A. Political instability B. Ergonomic issues C. Market demand D. Taxation changesarrow_forward8. Early warning indicators help businesses to A. Avoid legal actions B. Grow rapidly C. Detect potential risks D. Hire employees 9. A hazard-based risk includes A. Political instability B. Ergonomic issues C. Market demand D. Taxation changesarrow_forward10. Which risk category refers to taking advantage of a new opportunity despite potential challenges? A. Hazard B. Uncertainty C. Opportunity D. Strategicarrow_forward
- Understanding Management (MindTap Course List)ManagementISBN:9781305502215Author:Richard L. Daft, Dorothy MarcicPublisher:Cengage LearningManagement, Loose-Leaf VersionManagementISBN:9781305969308Author:Richard L. DaftPublisher:South-Western College Pub
- Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningFoundations of Business - Standalone book (MindTa...MarketingISBN:9781285193946Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningPractical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,