WBS Task Name Duration Another Bar 27 days Chart Total Free Float Jan 03 Jan 10 Jan 17 Jan 24 Float Predecessor ES LS EF LF REWTFSSMTWTFS SMTWTFS SMTWTFS SMTWT 0 days 0 days 01 01 27 27 Schedule 1 Deliverable 1 27 days 0 days 0 days 1.1 A 5 days O days 0 days 1.2 B 1 day 1 day O days A 1.3 Н 5 days O days O days C,F,G(FF) 2 Deliverable 2 15 days 1 day 1 day 2.1 C 15 days 1 day 1 day B 2.2 J 2 days 9 days 7 days E 3 Deliverable 3 20 days 0 days 0 days 3.1 3.2 3.3 3.4 DEFG 10 days O days O days A 11 days 2 days O days A 6682662888 07 17 7 days O days O days D 9 days 2 days 2 days EJ(FF) 01 01 27 01 01 05 27 06 07 06 07 23 23 27 27 07 5662882888 2 21 27 21 288222 286222222222 18 27 06 06 25 27 06 06 15 15 06 08 16 16 16 18 17 19 25 27 How would the critical path, float and project duration change if: Situation 1 2 3 Description D starts 3 days after A starts B can start 2 days after A starts F can start 5 days after D starts Dependency Will Critical Path Change? Project Duration Total Float Free Float On D On D On B On B On F On F
WBS Task Name Duration Another Bar 27 days Chart Total Free Float Jan 03 Jan 10 Jan 17 Jan 24 Float Predecessor ES LS EF LF REWTFSSMTWTFS SMTWTFS SMTWTFS SMTWT 0 days 0 days 01 01 27 27 Schedule 1 Deliverable 1 27 days 0 days 0 days 1.1 A 5 days O days 0 days 1.2 B 1 day 1 day O days A 1.3 Н 5 days O days O days C,F,G(FF) 2 Deliverable 2 15 days 1 day 1 day 2.1 C 15 days 1 day 1 day B 2.2 J 2 days 9 days 7 days E 3 Deliverable 3 20 days 0 days 0 days 3.1 3.2 3.3 3.4 DEFG 10 days O days O days A 11 days 2 days O days A 6682662888 07 17 7 days O days O days D 9 days 2 days 2 days EJ(FF) 01 01 27 01 01 05 27 06 07 06 07 23 23 27 27 07 5662882888 2 21 27 21 288222 286222222222 18 27 06 06 25 27 06 06 15 15 06 08 16 16 16 18 17 19 25 27 How would the critical path, float and project duration change if: Situation 1 2 3 Description D starts 3 days after A starts B can start 2 days after A starts F can start 5 days after D starts Dependency Will Critical Path Change? Project Duration Total Float Free Float On D On D On B On B On F On F
Chapter1: Taking Risks And Making Profits Within The Dynamic Business Environment
Section: Chapter Questions
Problem 1CE
Related questions
Question
Could you please explain the answers of each column to this question in detail according to the answer table I provided? Why the critical path will change, how the project duration will change and why the free float and total float are those number listed?

Transcribed Image Text:WBS Task Name
Duration
Another Bar 27 days
Chart
Total
Free
Float
Jan 03
Jan 10
Jan 17
Jan 24
Float Predecessor ES LS EF LF REWTFSSMTWTFS SMTWTFS SMTWTFS SMTWT
0 days 0 days
01 01 27 27
Schedule
1
Deliverable 1 27 days
0 days
0 days
1.1
A
5 days
O days
0 days
1.2
B
1 day
1 day
O days A
1.3
Н
5 days
O days
O days C,F,G(FF)
2
Deliverable 2 15 days
1 day
1 day
2.1
C
15 days
1 day
1 day
B
2.2
J
2 days
9 days
7 days E
3
Deliverable 3 20 days
0 days
0 days
3.1
3.2
3.3
3.4
DEFG
10 days
O days
O
days A
11 days
2 days
O days A
6682662888
07
17
7 days
O days
O
days D
9 days
2 days
2 days EJ(FF)
01 01 27
01 01
05
27
06 07 06 07
23 23 27 27
07
5662882888 2
21 27
21
288222
286222222222
18 27
06 06 25 27
06 06 15 15
06 08
16
16
16 18
17 19 25 27

Transcribed Image Text:How would the critical path, float and project duration change if:
Situation
1
2
3
Description
D starts 3 days after A
starts
B can start 2 days after
A starts
F can start 5 days after
D starts
Dependency
Will Critical
Path
Change?
Project
Duration
Total Float
Free Float
On D
On D
On B
On B
On F
On F
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps

Recommended textbooks for you

Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education

Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON

Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning

Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education

Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON

Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning

Management Information Systems: Managing The Digi…
Management
ISBN:
9780135191798
Author:
Kenneth C. Laudon, Jane P. Laudon
Publisher:
PEARSON

Business Essentials (12th Edition) (What's New in…
Management
ISBN:
9780134728391
Author:
Ronald J. Ebert, Ricky W. Griffin
Publisher:
PEARSON

Fundamentals of Management (10th Edition)
Management
ISBN:
9780134237473
Author:
Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:
PEARSON