Question Table 1 shows the list of the consecutive activities and their details for an 8-mi road construction project. Prepare a line of balance schedule for a contract of 125 sections using a target rate of build of 1.5 mile per week and each team working at their natural rate assume a minimum buffer time of 4 days between the operation and five 8 hrs days per week. 1. What is the overall duration of the project? 2. The date of the end of construction of 75% of the road. 3. The rate of work progress after 4 weeks. Activities Description Man hours Team size Depends on A Clearing 550 6 Grubbing 550 Earth work 460 A, B

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
icon
Concept explainers
Question
1%Vo lI. In.
7:08
Report.JPG
Question
Table 1 shows the list of the consecutive activities and their details for an 8-mi road
construction project. Prepare a line of balance schedule for a contract of 125 sections
using a target rate of build of 1.5 mile per week and each team working at their natural
rate assume a minimum buffer time of 4 days between the operation and five 8 hrs
days per week.
1. What is the overall duration of the project?
2. The date of the end of construction of 75% of the road.
3. The rate of work progress after 4 weeks.
Activities
Description
Man hours
Team size
Depends on
Clearing
550
B
Grubbing
550
5
Earth work
460
4.
A, B
D
Base
420
3
Paving
330
3
D
F
Finish Shoulders
200
1
E
Move out
180
1
>
Transcribed Image Text:1%Vo lI. In. 7:08 Report.JPG Question Table 1 shows the list of the consecutive activities and their details for an 8-mi road construction project. Prepare a line of balance schedule for a contract of 125 sections using a target rate of build of 1.5 mile per week and each team working at their natural rate assume a minimum buffer time of 4 days between the operation and five 8 hrs days per week. 1. What is the overall duration of the project? 2. The date of the end of construction of 75% of the road. 3. The rate of work progress after 4 weeks. Activities Description Man hours Team size Depends on Clearing 550 B Grubbing 550 5 Earth work 460 4. A, B D Base 420 3 Paving 330 3 D F Finish Shoulders 200 1 E Move out 180 1 >
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Pavement management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning