The _____ for an activity is the amount that its duration can slip without causing the project to be delayed.

  a.

Speed

  b.

Float

  c.

Stride

  d.

Pace

Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Types of Scheduling Techniques
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,