Question Table 1 shows the list of the consecutive activities and their details for an 8-mi road construction project. Prepare a line of balance schedule for a contract of 125 sections using a target rate of build of 1.5 mile per week and each team working at their natural rate assume a minimum buffer time of 4 days between the operation and five 8 hrs days per week. 1. What is the overall duration of the project? 2. The date of the end of construction of 75% of the road. 3. The rate of work progress after 4 weeks. Activities Description Man hours Team size Depends on A Clearing 550 B Grubbing 550 Earth work 460 4 А, В D Base 420 3 E Paving 330 F Finish Shoulders 200 1 G Move out 180 1 F
Question Table 1 shows the list of the consecutive activities and their details for an 8-mi road construction project. Prepare a line of balance schedule for a contract of 125 sections using a target rate of build of 1.5 mile per week and each team working at their natural rate assume a minimum buffer time of 4 days between the operation and five 8 hrs days per week. 1. What is the overall duration of the project? 2. The date of the end of construction of 75% of the road. 3. The rate of work progress after 4 weeks. Activities Description Man hours Team size Depends on A Clearing 550 B Grubbing 550 Earth work 460 4 А, В D Base 420 3 E Paving 330 F Finish Shoulders 200 1 G Move out 180 1 F
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
![Question
Table 1 shows the list of the consecutive activities and their details for an 8-mi road
construction project. Prepare a line of balance schedule for a contract of 125 sections
using a target rate of build of 1.5 mile per week and each team working at their natural
rate assume a minimum buffer time of 4 days between the operation and five 8 hrs
days per week.
1. What is the overall duration of the project?
2. The date of the end of construction of 75% of the road.
3. The rate of work progress after 4 weeks.
Activities
Description
Man hours Team size Depends on
A
Clearing
550
B
Grubbing
550
Earth work
460
4
А, В
Base
420
E
Paving
330
3
F
Finish Shoulders
200
1
E
Move out
180
1
F
6,](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F24e29cc4-b919-4ed9-a535-106f37ca65d1%2F7ef8f9b5-f601-4788-8afe-9151ee8909d1%2F8khd8lg_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Question
Table 1 shows the list of the consecutive activities and their details for an 8-mi road
construction project. Prepare a line of balance schedule for a contract of 125 sections
using a target rate of build of 1.5 mile per week and each team working at their natural
rate assume a minimum buffer time of 4 days between the operation and five 8 hrs
days per week.
1. What is the overall duration of the project?
2. The date of the end of construction of 75% of the road.
3. The rate of work progress after 4 weeks.
Activities
Description
Man hours Team size Depends on
A
Clearing
550
B
Grubbing
550
Earth work
460
4
А, В
Base
420
E
Paving
330
3
F
Finish Shoulders
200
1
E
Move out
180
1
F
6,
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 5 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning