CRITICAL PATH SAMPLE PROBLEM: Given the following data for a certain construction determine the critical path, the total duration of the project in weeks. Nodes Activity 1-2 a. demolition and clearing 23 b. excavation 2-5 c. underground installations 3-4 d. foundations & columns 4-5 e. DUMMY 46 f. construction of second floor 4-7 g. roof framing and roofing 5-7 h. ground floorslab 58 i. Mechanical and elelctrical services 6 7 j. construction of exterior walls 7-8 k. DUMMY 7-9 1. construction of interior partitions 8-9 m. Mechanical and electrical fixtures 9-10 n painting and finishing Time (weeks) 8 14 6 5 0 6 6 4 12 12 0 10 12 8 Draw the project duration using the nodes and place the time in weeks, as can be seen a dummy activity is present for activity e and k which simply means you cannot go to e unless d is done first.

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter16: Budget Estimating
Section: Chapter Questions
Problem 4RQ: Prepare a typical bay estimate based on the following information: a. Bay size of 350 feet and a...
icon
Related questions
Question
CRITICAL PATH SAMPLE PROBLEM: Given the following data for a certain construction
determine the critical path, the total duration of the project in weeks.
Nodes
Activity
1-2 a. demolition and clearing
23 b. excavation
2-5 c. underground installations
3-4 d. foundations & columns
4-5 e. DUMMY
46 f. construction of second floor
4-7 g. roof framing and roofing
5-7 h. ground floorslab
5-8 i. Mechanical and elelctrical services
6 7 j. construction of exterior walls
7-8 k. DUMMY
7-9 1. construction of interior partitions
8-9 m. Mechanical and electrical fixtures
9 10 n painting and finishing
Time (weeks)
8
14
6
5
0
6
6
4
12
12
0
10
12
8
Draw the project duration using the nodes and place the time in weeks, as can
be seen a dummy activity is present for activity e and k which simply means you
cannot go to e unless d is done first.
Transcribed Image Text:CRITICAL PATH SAMPLE PROBLEM: Given the following data for a certain construction determine the critical path, the total duration of the project in weeks. Nodes Activity 1-2 a. demolition and clearing 23 b. excavation 2-5 c. underground installations 3-4 d. foundations & columns 4-5 e. DUMMY 46 f. construction of second floor 4-7 g. roof framing and roofing 5-7 h. ground floorslab 5-8 i. Mechanical and elelctrical services 6 7 j. construction of exterior walls 7-8 k. DUMMY 7-9 1. construction of interior partitions 8-9 m. Mechanical and electrical fixtures 9 10 n painting and finishing Time (weeks) 8 14 6 5 0 6 6 4 12 12 0 10 12 8 Draw the project duration using the nodes and place the time in weeks, as can be seen a dummy activity is present for activity e and k which simply means you cannot go to e unless d is done first.
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Dimensional homogeneity
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Construction Materials, Methods and Techniques (M…
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning