Calculate the contract value, the monthly value of the planned work to be completed (Budget value) and the monthly amounts (payments) that expected to be received (Expected payments) If the ratio of profit that the contractor desires is (15%) and the contract for this type of project provides for the deduction of the amount of 5% (retention rate) from value of monthly payments to pay 50 of the total deductions upon completion of the work and pay the remaining 50 after the end of the maintenance period of 3 months and the first monthly payment received after one month from the start of the project, Draw the curves of the value of the planned work done and the amounts expected to be received.

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter14: Pricing General Expenses
Section: Chapter Questions
Problem 4RQ
icon
Related questions
Question
Q3/ A construction project have the following data in the table below:-
Activity Duration
(weeks)
Activity total
cost ($)
400
Critical Activity
Dependency
A
----
В
5
350
----
C
3
A
300
D
3
В
450
E
12
960
----
F
15
A, B
600
Total project cost = E Activity total cost ($)
3060
%3D
Required:-
Calculate the contract value, the monthly value of the planned work to be completed
(Budget value) and the monthly amounts (payments) that expected to be received
(Expected payments) If the ratio of profit that the contractor desires is (15%) and the
contract for this type of project provides for the deduction of the amount of 5% (retention
rate) from value of monthly payments to pay 50 of the total deductions upon completion of
the work and pay the remaining 50 after the end of the maintenance period of 3 months
and the first monthly payment received after one month from the start of the project, Draw
the curves of the value of the planned work done and the amounts expected to be received.
Transcribed Image Text:Q3/ A construction project have the following data in the table below:- Activity Duration (weeks) Activity total cost ($) 400 Critical Activity Dependency A ---- В 5 350 ---- C 3 A 300 D 3 В 450 E 12 960 ---- F 15 A, B 600 Total project cost = E Activity total cost ($) 3060 %3D Required:- Calculate the contract value, the monthly value of the planned work to be completed (Budget value) and the monthly amounts (payments) that expected to be received (Expected payments) If the ratio of profit that the contractor desires is (15%) and the contract for this type of project provides for the deduction of the amount of 5% (retention rate) from value of monthly payments to pay 50 of the total deductions upon completion of the work and pay the remaining 50 after the end of the maintenance period of 3 months and the first monthly payment received after one month from the start of the project, Draw the curves of the value of the planned work done and the amounts expected to be received.
Expert Solution
steps

Step by step

Solved in 4 steps with 5 images

Blurred answer
Knowledge Booster
Taxable income
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,