In the given project, the expected markup is 30%, four payments are expected to be paid to the contractor. The first three payments are expected to be as the following; first payment is 12,000 at the end of the first month; second payment is 16,000 at the end of second month, and third payment is 22,000 at the end of fourth month. the value of the fourth payment assuming it will be paid at the end of the fifth month, assuming 10% retentions, and that retentions will be paid back to the contractor at the end of the sixth month? Neglect resources distribution in this project. Solve 9-14. Find the project gross profit. Duration Activity Activity cost Predecessor Relationship (months) 1 20,000 20,000 50,000 10,000 FS FS+1 C 2 1 C FS Answer:

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question

Please give me both answers as soon as possible. Thank you

In the given project, the expected markup is 30%, four payments are expected to be paid to the contractor. The first three payments are
expected to be as the following; first payment is 12,000 at the end of the first month; second payment is 16,000 at the end of second
month, and third payment is 22,000 at the end of fourth month. the value of the fourth payment assuming it will be paid at the end of
the fifth month, assuming 10% retentions, and that retentions will be paid back to the contractor at the end of the sixth month? Neglect
resources distribution in this project. Solve 9-14.
Find the project gross profit.
Duration
Activity
cost
20,000
,000
50,000
10,000
Activity
PredecessorRelationship
(months)
1.
1
A
FS
C
FS+1
FS
Answer:
Find the project price.
Answer:
Transcribed Image Text:In the given project, the expected markup is 30%, four payments are expected to be paid to the contractor. The first three payments are expected to be as the following; first payment is 12,000 at the end of the first month; second payment is 16,000 at the end of second month, and third payment is 22,000 at the end of fourth month. the value of the fourth payment assuming it will be paid at the end of the fifth month, assuming 10% retentions, and that retentions will be paid back to the contractor at the end of the sixth month? Neglect resources distribution in this project. Solve 9-14. Find the project gross profit. Duration Activity cost 20,000 ,000 50,000 10,000 Activity PredecessorRelationship (months) 1. 1 A FS C FS+1 FS Answer: Find the project price. Answer:
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Steel
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning