Q1: Discuss “Contract System” of CNW KPK for civil construction work from inviting of tender to allotment of work.
Q: job in the completion stage can be completed in 40 days of 8hrs work per day with 40 men working…
A:
Q: Typical standard form of contract enables the contract administrator to approve the extensions of…
A:
Q: a) Discuss the principal/primary contractual roles of the client and contractor under the…
A: Under conventional construction contracts, there are generally two primary parties involved:the…
Q: Does the work covered in a construction contract include a stated gaurantee period?
A: The contract is a legal agreement which is signed between two or more parties. The limitation period…
Q: (a) Design-bid-build is a sequential process to deliver a construction project. Produce a short…
A: Step : 1 Design-bid-build :- It is a sequential process to deliver a construction project where one…
Q: What means are available to a contractor bidding a unit-price project for recovery of “General…
A: Front loading bids, unbalancing bids to retrieve mobilization costs. Owners set lump sum amounts for…
Q: What is the usual criterion that governs selection of the successful bidder in a public works…
A: Here are the conditions for this.
Q: T or F The Owner's level of risk, as well as their level of control, is highest on a…
A: Note:- Hi! Thank you for the question, As per the honor code, we are allowed to answer three…
Q: Once the drawings and specifications complete, a design-build contract can be rolled over into a(n)…
A: By contrast, in design-build the contractor warrants to the owner that the designdocuments are…
Q: Why should the public works projects,not allowed of any substitutions between the bid-opening…
A: Bid-opening contract is not an agreement and is neither an offer nor invitation by the nodal agency…
Q: As a construction project manager, what general categoriesof information would you want to have on a…
A: As a construction project manager in order to properly evaluate what i think is a developing overrun…
Q: Discuss overlap and underlap of subcontracted work and the problems associated with each condition.
A: It is very important that all of the project work must be completed, examined, and executed by…
Q: In construction, Identify a risk. Explain the nature of the risk and its magnitude. Provide all…
A:
Q: . Describe the three types of authorities exercised in a construction contract?
A: Three types of authorities exercised in a construction contract are : 1.Actual Authority : It is…
Q: 1. Four legal components are required for construction contracts to be valid include 2. The…
A: We need to complete the given sentances relatd to construction contracts.
Q: Match the examples with "PHYSICAL, BIOLOGICAL, ERGONOMIC, CHEMICAL" hazard categories. Poisonous…
A:
Q: Determine the criteria for the selection of a contract. Time Cost Quality Risk
A: Brief concept introduction- Contract- A contract is an agreement between two parties that is…
Q: . True or False? A payment bond provides the construction contractor a guarantee that they will…
A: Construction works include demolition, erection and repair of structures and civil works.…
Q: ucture and building foundations for Short’s new factory for a stated percentage of the contract…
A: The design and construction of super structure depends on the type of foundation used. Planning and…
Q: Name and briefly describe each of the two basic types ofcompetitively bid construction contracts.…
A: Answer The two basic type of competitively bid construction contracts 1) The lump-sum contract 2)…
Q: Contractor A fails to complete the contracted Work for a project based on the contract drawings and…
A:
Q: The estimated cost of the foundation works was RM 780,650 in the year 2006 and RM 920,500 in the…
A:
Q: Construction cost engineering What your learnings on the preparation of program of works and for the…
A: Cost engineering is "the engineering practice devoted to the management of project cost, involving…
Q: Question Table 1 shows the list of the consecutive activities and their details for an 8-mi road…
A: Given:- Target rate of the build = 1.5 miles per week Minimum buffer time = 4 days To determine:=…
Q: 6. Describe and provide and example of the most appropriate situation for the following: a) but-for…
A: As per the guidelines, I will answer the first question only. Please upload other questions as a…
Q: Classify the under listed instances into the appropriate types of contracts. a. A standard form of…
A: Where Particular Conditions can be used, FIDIC contracts provide guidelines on project-specific…
Q: Salary of foreman in a project is considered as direct labor t or f
A: Given Statement : Salary of foreman in a project is considered as direct labour----
Q: At what conditions can the contractor appeal for a suspension of work?
A: Explanation- Absolutely, the Contractors may suspend or cancel the Contract with fifteen (15) days'…
Q: 3. The total of Bill to owner on project cash flow must cqual on pay application G702 and on pay…
A: Given:- The total of Bill to owner on project cash flow must equal...........On pay application G702…
Q: Question Table 1 shows the list of the consecutive activities and their details for an 8-mi road…
A:
Q: Under what circumstances is a cost-plus contract favorableto both owner and contractor?
A: The cost plus style of contracts has a variety of a reimbursement schemes used to pay for the…
Q: 8.4. Determine the cost to install 126 tons of structural steel given the following infor- mation:…
A:
Q: Question 14: What is a key characteristic of the preconstruction stage? o walkdown of the site o…
A: 14) procurement 15) False The wrong judged prices will be equally shared by both contractor and…
Q: An engineer serves as the sole point contact with a state agency accepting bids for an upcoming…
A: Answer - C - Report the company , return the tickets and reject the bid.
Q: Who is responsible for contracting for subcontractor services for construction on a project? a.…
A: Following is required answer :
Q: Labb Construction Co. has recently won a bid to construct a building that will serve as an…
A:
Q: Suppose you are an engineer in the real estate department of a foreign bank. The bank desire to give…
A: In-order to clearly determine the type of contract that has to be proposed and accepted by the…
Q: Q1/ Answer by true or false (T or F) of TEN of the following: 1- The main contractor does not need…
A: Some statements regarding contractors are given. We need to state whether they are true or…
Q: Visit a local building contractor and determine how he orshe handles control of submittals from…
A: According to qusetion; As a construction and material testing (CMT) engineer, I had been working…
Q: Discuss the primary advantages and disadvantages of bidding for: (a) public work; (b) private work.
A: Tendering Process under development is a course of presenting a proposition to attempt government…
Q: Two installers will install the unit. Each will work the same amount of timeand will be paid $8.00…
A: Given:- paid amount=$8.00 per hour two installers each work same amount of time To find:- how much…
Q: 2. In any given construction scenario a limited number of days can be taken out of the schedule…
A: The theoretical limit of shortening a construction schedule is defined by the critical path of the…
Q: shows the project organization chart for a Design-Bid-Build project delivery method. Assume the same…
A: Design Bid Build: The owner has to seek out each company separately. The architect and general…
Q: What are the benefits of public works contracts for the contractor?
A: The public works contracts are the contracts for financial interest decided in writing between a…
Q: From where the temporary construction utility services are obtained?
A: Temporary construction utility includes all the facilities which are required at the construction…
![](/static/compass_v2/shared-icons/check-mark.png)
Step by step
Solved in 3 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
- The free-haul distance in a highway construction contract is 150m and theoverhaul price is $15/m3 .station. determine the extra compensation that must be paid to the contractor to balance the cut and fill between balance points (A) and (B) and (B) and (C).As the construction manager/Site engineer, there are many issues that have come up at management meetings. These include; The company paying more for labour than the market rate or what was billed in the BoQ. Investigations showed that the foreman and time keeper connived to overbill or mark artisans more than they deserve and there were cases where artisans who never worked were marked as present. Materials are procured at non-competitive prices and some materials procured do not suffice the assigned. In addition, some materials do not reach site or are taken away from site prematurely and are not traceable. Provide a solution to this problemActivity 1. A bungalow house with a floor area of 50 square meters is to be built by a crew composed a foreman, 5 skilled workers and 3 laborers for an estimated duration of 100 construction days. Considering a Php 16,000.00 cost per square meter, what is the total project cost if the crew is to be paid at the following rates: foreman (700 pesos per day), skilled worker (500 pesos per day), and laborer (300 pesos per day)?
- Engr. David is holding a permanent position as Engineer II in the Department of Public Works and Highways (DPWH). DPWH enters into a contract with Red Mole Construction (CONTRACTOR) for the construction of a school building. The Contractor wants to engage the services of Engr. David as a consultant for the project. As a form of compensation, Engr. David will be paid a percentage of the contract amount of the project. Will the said engagement be violative of the Code of Ethics of Civil Engineers and existing laws, rules and regulations?You are currently working in one of the prefabricated building manufacturers. Your company had been appointed for a 5-storey building construction project, which will be fully using BIM and IBS. However, your company is still new to BIM. Since you have good background in BIM, your company had instructed you to lead the project team on using BIM to manufacture the IBS component for the project. a) To ease the costing process, the company had decided to use the BIM model to estimate the total cost of the project. Explain any 2 approaches that can be used to extract the quantities from the BIM modelDiscuss with reference to Clauses in the Conditions of Contract (FIDIC for Building and Engineering Work designed by the Employer fourth edition 1987) how the underlisted general provisions in the General Conditions Contract can be modified in the Conditions of Particular Application to allows proper contract management to reflect the desires of the Client.a) Programmeb) Epidemicsc) Suspension of Workd) Completion Timee) Bonus for Completion
- Is it advisable to use cost-loaded CPM for progress payments to the contractor on unit-price contracts?In a construction project, when does the maximum need for cash arise during any month? a) At the end of the month before payment is received from the owner At the beginning of the month At the end of the month after payment is received from the owner During mid-month b) c) d) e) At the beginning of the projectAdvantage of Measured or Unit rate Contract اختر أحد الخيارات a. the tender sum tells him the exact cost of the project. Sometimes the employer will be working within a tight margin of budget O b. The employer pays for the actual work executed Ⓒ c. No conflicts will be anticipated as to extras or omissions d. Both parties need a smaller number of staff for book-keeping accounting and measurement
- If the engineer or the owner disputes the work being performed by a subcontractor, with which party should the owner attempt to resolve the issue?If the direct cost of materials, labor and equipment of CHB (4") laying work for 102.14 sq.m is Php 84,740.15. What is the unit cost per square meter if you are to include 15% profit?14. A contractor undertook to complete a piece of work in 120 days and employed 140 men upon it. At the end of 66 days only half of the work was done, so he put on 25 extra men. By much time did he exceed the specified time? (a) I (d) 4 (c) 3 (b) 2 of work
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)