. An equipment installation job can be completed in 50 days of 8 hour/day work, with 50 men working. With the contract expiring in 40 days and overtime not permitted, the mechanical engineer-contractor decided to add 15 men on the job. If the liquidated damages are P5000.00/day of delay, and the men are paid P150.00/day, how much money would he save with the additional workers?
. An equipment installation job can be completed in 50 days of 8 hour/day work, with 50 men working. With the contract expiring in 40 days and overtime not permitted, the mechanical engineer-contractor decided to add 15 men on the job. If the liquidated damages are P5000.00/day of delay, and the men are paid P150.00/day, how much money would he save with the additional workers?
Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter13: Pricing Subcontractors' Work
Section: Chapter Questions
Problem 2RQ
Related questions
Question
Engineering Economics 00010
Please provide a solution for this problem
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 2 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,