A project of Glam Rock Industries involves making a small concert hall. The contractor pays 40000php and additional 9000php on every week spent on this project. Having considered the materials and equipment cost and the laborers' paycheck, only the project-in-charge and taxes are getting weighed. Workers are not allowed to make any movement unless supervised by the project-in-charge (PIC) so the project stops if the PIC is not around. 3 engineers are
A project of Glam Rock Industries involves making a small concert hall. The contractor pays 40000php and additional 9000php on every week spent on this project. Having considered the materials and equipment cost and the laborers' paycheck, only the project-in-charge and taxes are getting weighed. Workers are not allowed to make any movement unless supervised by the project-in-charge (PIC) so the project stops if the PIC is not around. 3 engineers are
Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter11: Pricing Concrete Work
Section: Chapter Questions
Problem 9RQ: Calculate the cost per cubic yard to place concrete using each of the alternatives described. The...
Related questions
Question
Civil engineering
![A project of Glam Rock Industries involves making a small
concert hall. The contractor pays 40000php and additional
9000php on every week spent on this project. Having
considered the materials and equipment cost and the
laborers' paycheck, only the project-in-charge and taxes are
getting weighed. Workers are not allowed to make any
movement unless supervised by the project-in-charge (PIC) so
the project stops if the PIC is not around. 3 engineers are
referred as project-in-charge by reliable connections and the
contractor can only choose one;
Firehouse Firm referred CJ, a very strict PIC who finishes 0.4%
of the entire project every hour, but is only available 5 hours
daily on weekdays. Has a rate of 1400php/hr.
Bad English Firm referred Johnny, a very calm PIC who finishes
0.28% of the entire project every hour, but is only available 4
hours every day. Has a rate of 920php/hr.
Steelheart Firm referred Miljenko, a very fine and attentive PIC
who finishes 0.25% of the entire project every hour but works
only for 10 hours TThS schedule to spend more time with his
family. Has a rate of 800php/hr
Arrange the PICs from the cheapest to the most expensive
considering the total cost.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F61eace19-5208-4d7c-b163-5994a2f0f7bd%2F4efa65ae-dd76-4e87-a842-d05e024870fa%2Fjyv9cea_processed.jpeg&w=3840&q=75)
Transcribed Image Text:A project of Glam Rock Industries involves making a small
concert hall. The contractor pays 40000php and additional
9000php on every week spent on this project. Having
considered the materials and equipment cost and the
laborers' paycheck, only the project-in-charge and taxes are
getting weighed. Workers are not allowed to make any
movement unless supervised by the project-in-charge (PIC) so
the project stops if the PIC is not around. 3 engineers are
referred as project-in-charge by reliable connections and the
contractor can only choose one;
Firehouse Firm referred CJ, a very strict PIC who finishes 0.4%
of the entire project every hour, but is only available 5 hours
daily on weekdays. Has a rate of 1400php/hr.
Bad English Firm referred Johnny, a very calm PIC who finishes
0.28% of the entire project every hour, but is only available 4
hours every day. Has a rate of 920php/hr.
Steelheart Firm referred Miljenko, a very fine and attentive PIC
who finishes 0.25% of the entire project every hour but works
only for 10 hours TThS schedule to spend more time with his
family. Has a rate of 800php/hr
Arrange the PICs from the cheapest to the most expensive
considering the total cost.
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 3 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Fundamentals Of Construction Estimating](https://www.bartleby.com/isbn_cover_images/9781337399395/9781337399395_smallCoverImage.gif)
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
![Solid Waste Engineering](https://www.bartleby.com/isbn_cover_images/9781305635203/9781305635203_smallCoverImage.gif)
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,
![Fundamentals Of Construction Estimating](https://www.bartleby.com/isbn_cover_images/9781337399395/9781337399395_smallCoverImage.gif)
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
![Solid Waste Engineering](https://www.bartleby.com/isbn_cover_images/9781305635203/9781305635203_smallCoverImage.gif)
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,