Q3: A company awarded a contract to erect 124 electrical towers the table below shows the sequential operation also the estimated man-hours and optimum number of men/operation the hand over is 6 towers/weeks prepare a line of balance schedule assuming 5 working days/week and 8 hours/day, the minimum buffer time 3 day Activity Q(Optimum ofmen/operation 4. Man-hour Description Excavation 55 A. 64 4. Implementation foundation Installing the Tower Cable arm fixing Insulator fixing of reinforced concrete 145 8. 90 8. D. 25 Determine the completion date of the project Determine the completion date of the installing Towers Determine the percentage completion of the project when 83% of the electrical tower have been installed. i- iii-

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
Q3: A company awarded a contract to erect 124 electrical towers the table below shows the
sequential operation also the estimated man-hours and optimum number of men/operation
the hand over is 6 towers/weeks prepare a line of balance schedule assuming 5 working
days/week and 8 hours/day, the minimum buffer time 3 day
Activity
Man-hour
Q(Optimum ofmen/operation
Description
Excavation
55
64
4.
Implementation
foundation
of
reinforced
concrete
145
8
Installing the Tower
Cable arm fixing
Insulator fixing
90
8.
25
Determine the completion date of the project
Determine the completion date of the installing Towers
Determine the percentage completion of the project when 83% of
the electrical tower have been installed.
ii-
iii-
Transcribed Image Text:Q3: A company awarded a contract to erect 124 electrical towers the table below shows the sequential operation also the estimated man-hours and optimum number of men/operation the hand over is 6 towers/weeks prepare a line of balance schedule assuming 5 working days/week and 8 hours/day, the minimum buffer time 3 day Activity Man-hour Q(Optimum ofmen/operation Description Excavation 55 64 4. Implementation foundation of reinforced concrete 145 8 Installing the Tower Cable arm fixing Insulator fixing 90 8. 25 Determine the completion date of the project Determine the completion date of the installing Towers Determine the percentage completion of the project when 83% of the electrical tower have been installed. ii- iii-
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Work breakdown structure
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning