Develop a programming budget estimate for a 100,000 square-foot warehouse, assuming a square-foot cost factor of $60 per square foot. The site will be about 200,000 square feet with a site development cost of $3 per square foot. Use the following allowances to prepare your budget estimate: - Owner-furnished FFE: $1,000,000 - Owner soft costs: $800,000 - Programming fees: $50,000 - Geotechnical Investigation: $390,000
Develop a programming budget estimate for a 100,000 square-foot warehouse, assuming a square-foot cost factor of $60 per square foot. The site will be about 200,000 square feet with a site development cost of $3 per square foot. Use the following allowances to prepare your budget estimate: - Owner-furnished FFE: $1,000,000 - Owner soft costs: $800,000 - Programming fees: $50,000 - Geotechnical Investigation: $390,000
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
Develop a programming budget estimate for a 100,000 square-foot warehouse, assuming a square-foot cost factor of $60 per square foot. The site will be about 200,000 square feet with a site development cost of $3 per square foot. Use the following allowances to prepare your budget estimate:
- Owner-furnished FFE: $1,000,000
- Owner soft costs: $800,000
- Programming fees: $50,000
- Geotechnical Investigation: $390,000

Transcribed Image Text:16 * Fill out the cells in Yellow
17
18 Project:
100,000sqft Warehouse
19 Estimator:
20 Estimate Date:
January 0, 1900
21
22
Programming Budget Estimate
23
24
Scope
Unit Price
Total
25 Building Construction
26 Site Development
Subtotal (Construction Cost)
28 Programming Fees
29 Design Fees
30 Geotechnical Investigation
31 Testing & Inspection Fees
32 Permits & Fees
33 Insurance
Owner-Furnished Furniture, Fixtures
34 & Equipment
35 Owner Soft Cost
Subtotal (Costs)
27
Allowance
6% of Construction Cost
Allowance
3% of Construction Cost
2% of Construction Cost
2% of Construction Cost
Allowance
Allowance
36
37 Sales Tax
8% of Subtotal
38 Owner Contingency
20% of Subtotal
39
Total Budget Estimate
40
41
42
43
Exercise 1
+)
Ready
O Type here to search
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education


Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning