1. Given the following construction progress chart, calculate the weekly cumulative progress and show the curve on the chart. The total project labor hours is 33,985, the percent complete shown is actual progress. You must calculate the weight of each activity. Operation 1. Clear and Grubbing 2. Drainage 3. Subgrade Shows planned schedule Shows actual progress 5. Pave Hours Wt. 1625 405 8745 4. Base Course 8125 14005 SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT 1 15 2 50 30 15 3 80 60 40 4 100 100 65 Weeks 5 6 10 30 7 8 9 How to calculate the weight for each activity: The individual weight is simply what percentage is the activity of the total project labor hours. 10 100% 90% 80% 70% 60% 50% 40% 30% 20% 10%

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
icon
Concept explainers
Question
1. Given the following construction progress chart, calculate the weekly cumulative progress
and show the curve on the chart. The total project labor hours is 33,985, the percent
complete shown is actual progress. You must calculate the weight of each activity.
Operation
1. Clear and
Grubbing
2. Drainage
3. Subgrade
Shows planned schedule
Shows actual progress
5. Pave
Hours Wt.
1625
405
8745
4. Base Course 8125
14005
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
1
15
2
50
30
15
3
80
60
40
4
100
100
65
Weeks
5
6
10
30
7
8
9
How to calculate the weight for each activity: The individual weight is simply what percentage
is the activity of the total project labor hours.
10
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
Transcribed Image Text:1. Given the following construction progress chart, calculate the weekly cumulative progress and show the curve on the chart. The total project labor hours is 33,985, the percent complete shown is actual progress. You must calculate the weight of each activity. Operation 1. Clear and Grubbing 2. Drainage 3. Subgrade Shows planned schedule Shows actual progress 5. Pave Hours Wt. 1625 405 8745 4. Base Course 8125 14005 SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT 1 15 2 50 30 15 3 80 60 40 4 100 100 65 Weeks 5 6 10 30 7 8 9 How to calculate the weight for each activity: The individual weight is simply what percentage is the activity of the total project labor hours. 10 100% 90% 80% 70% 60% 50% 40% 30% 20% 10%
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Pricing concrete work
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning