Activities A and B are the first two activities of a project. Activity A takes 20 days to complete (5 day a week, 8 hour a day [5/40]) with a 6-member crew at an average hourly rate of $45. Activity B takes 14 days to complete, working 5/40 with a crew of 3 at an average hourly rate of $60. Both activities must be completed by day 30. Both activities are interruptible. Activity A has a critical Early Start at day 0, and non-critical Late Finish at day 30 Activity B is non-critical and it has a SS relationship with activity A, with 6 days of lag, and a LF at day 30. Material usage for activity A is 450 units per day, at $650/unit. (Waste included) Material usage for activity B is 1500 units per day, at $950/unit. (Waste included) Activity A uses 40% of a backhoe, at $1995/day. Activity B uses 60% of a pump truck, at $2500/day. a. Calculate the total cost of activities A and B combined.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question

only do part A

1. Activities A and B are the first two activities of a project. Activity A takes 20 days to
complete (5 day a week, 8 hour a day [5/40]) with a 6-member crew at an average
hourly rate of $45. Activity B takes 14 days to complete, working 5/40 with a crew of 3,
at an average hourly rate of $60.
Both activities must be completed by day 30.
Both activities are interruptible.
Activity A has a critical Early Start at day 0, and non-critical Late Finish at day 30
Activity B is non-critical and it has a SS relationship with activity A, with 6 days of lag,
and a LF at day 30.
Material usage for activity A is 450 units per day, at $650/unit. (Waste included)
Material usage for activity B is 1500 units per day, at $950/unit. (Waste included)
Activity A uses 40% of a backhoe, at $1995/day.
Activity B uses 60% of a pump truck, at $2500/day.
a. Calculate the total cost of activities A and B combined.
b. Provide a bar chart for the most optimum cash flow and labor utilization. Show the
daily values for both at the bottom of the bar chart.
Transcribed Image Text:1. Activities A and B are the first two activities of a project. Activity A takes 20 days to complete (5 day a week, 8 hour a day [5/40]) with a 6-member crew at an average hourly rate of $45. Activity B takes 14 days to complete, working 5/40 with a crew of 3, at an average hourly rate of $60. Both activities must be completed by day 30. Both activities are interruptible. Activity A has a critical Early Start at day 0, and non-critical Late Finish at day 30 Activity B is non-critical and it has a SS relationship with activity A, with 6 days of lag, and a LF at day 30. Material usage for activity A is 450 units per day, at $650/unit. (Waste included) Material usage for activity B is 1500 units per day, at $950/unit. (Waste included) Activity A uses 40% of a backhoe, at $1995/day. Activity B uses 60% of a pump truck, at $2500/day. a. Calculate the total cost of activities A and B combined. b. Provide a bar chart for the most optimum cash flow and labor utilization. Show the daily values for both at the bottom of the bar chart.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Work breakdown structure
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning