The contractor implements last planner on the project. During week 1, the following tasks are planned and committed by different subcontractors. At the end of week 1, the status of the tasks is also shown in the following table. What is the percent plan complete (PPC) for week 1? Explain what PPC measures? Committed on Completion Progress Completion? Mobilize Yes 100% Yes Install Security Fence Yes 100% Yes Set Forms Yes 80% No Excavate Planter Foundation Yes 100% Yes Construct Masonry Planter Yes 50% No
The contractor implements last planner on the project. During week 1, the following tasks are planned and committed by different subcontractors. At the end of week 1, the status of the tasks is also shown in the following table. What is the percent plan complete (PPC) for week 1? Explain what PPC measures? Committed on Completion Progress Completion? Mobilize Yes 100% Yes Install Security Fence Yes 100% Yes Set Forms Yes 80% No Excavate Planter Foundation Yes 100% Yes Construct Masonry Planter Yes 50% No
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
- The contractor implements last planner on the project. During week 1, the following tasks are planned and committed by different subcontractors. At the end of week 1, the status of the tasks is also shown in the following table. What is the percent plan complete (PPC) for week 1? Explain what PPC measures?
|
Committed on Completion |
Progress |
Completion? |
Mobilize |
Yes |
100% |
Yes |
Install Security Fence |
Yes |
100% |
Yes |
Set Forms |
Yes |
80% |
No |
Excavate Planter Foundation |
Yes |
100% |
Yes |
Construct Masonry Planter |
Yes |
50% |
No |
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education


Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning