Engr-429 Construction Management 1. Given the following construction progress chart, calculate the weekly cumulative progress through the end of week 5, and show the curve on the chart. The total project labor hours is 33,985, the percent complete shown is actual progress for each activity. You must calculate the weight of each activity. Shows planned schedule Shows actual progress Operation 1. Clear and Grubbing 2. Drainage 3. Subgrade 5. Pave 6. Testing Hours Wt. 7. Striping 1625 4. Base Course 8125 405 8745 14005 280 500 8. Punch List 400 SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT 1 10 2 40 30 15 3 80 160 30 4 100 100 55 Weeks 5 6 15 85 40 15 Fall 2023 7 8 9 10 The individual weight is simply the percentage the activity represents of the total project labor hours. 100% 90% 80% 70% 60% 50% 40% 30% 20% 10%
Engr-429 Construction Management 1. Given the following construction progress chart, calculate the weekly cumulative progress through the end of week 5, and show the curve on the chart. The total project labor hours is 33,985, the percent complete shown is actual progress for each activity. You must calculate the weight of each activity. Shows planned schedule Shows actual progress Operation 1. Clear and Grubbing 2. Drainage 3. Subgrade 5. Pave 6. Testing Hours Wt. 7. Striping 1625 4. Base Course 8125 405 8745 14005 280 500 8. Punch List 400 SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT 1 10 2 40 30 15 3 80 160 30 4 100 100 55 Weeks 5 6 15 85 40 15 Fall 2023 7 8 9 10 The individual weight is simply the percentage the activity represents of the total project labor hours. 100% 90% 80% 70% 60% 50% 40% 30% 20% 10%
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question

Transcribed Image Text:Engr-429 Construction Management
1. Given the following construction progress chart, calculate the weekly cumulative progress
through the end of week 5, and show the curve on the chart. The total project labor hours is
33,985, the percent complete shown is actual progress for each activity. You must calculate
the weight of each activity.
Shows planned schedule
Shows actual progress
Operation
1. Clear and
Grubbing
2. Drainage
3. Subgrade
5. Pave
6. Testing
Hours Wt.
7. Striping
1625
4. Base Course 8125
405
8745
14005
280
500
8. Punch List 400
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
SCH
ACT
1
10
2
40
30
15
3
80
160
30
4
100
100
55
Weeks
5
6
15
85
40
15
Fall 2023
7 8 9 10
The individual weight is simply the percentage the activity represents of the total project labor
hours.
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 3 images

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education


Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning