Consider a simple project in which four activities describe the basic tasks. This project is presented here as a bar chart drawn as a time-scaled schedule. The sum of the amounts for the activities in the schedule of values approximates the original anticipated cost of the project. The project duration is 5 weeks.   After 3 weeks, the following has been accomplished: Activity A-> 100 Percent complete, total cost $900 Activity B-> 40 percent complete, cost to date $1,400 Activity C-> 50 percent complete, cost to date $1,500 For this project, using earned value concepts, determine the schedule variance and the cost variance. State if the project is over or under budget and if it is ahead of or behind schedule.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question

Consider a simple project in which four activities describe the basic tasks. This project is presented here as a bar chart drawn as a time-scaled schedule. The sum of the amounts for the activities in the schedule of values approximates the original anticipated cost of the project. The project duration is 5 weeks.

 

After 3 weeks, the following has been accomplished:
Activity A-> 100 Percent complete, total cost $900

Activity B-> 40 percent complete, cost to date $1,400

Activity C-> 50 percent complete, cost to date $1,500

For this project, using earned value concepts, determine the schedule variance and the cost variance. State if the project is over or under budget and if it is ahead of or behind schedule.

Activity
Week
1
Week
3
Week
4
Cost
Week
2
Week
5
A. Brush clearing
$1,000
B. Tree cutting and removal
$3,000
C. Fencing
$1,500
D. Site grading
$2,500
Transcribed Image Text:Activity Week 1 Week 3 Week 4 Cost Week 2 Week 5 A. Brush clearing $1,000 B. Tree cutting and removal $3,000 C. Fencing $1,500 D. Site grading $2,500
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Cost control
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning