For the S-Curve below you received on a project, you can deduce: a. At week 25 the project is ahead of schedule b. At week 15 the project is ahead of schedule c. For weeks 16 and 17 no work was accomplished d. The workforce will have to work extra shifts to finish the project on schedule.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question

For the S-Curve below you received on a project, you can deduce:
a. At week 25 the project is ahead of schedule
b. At week 15 the project is ahead of schedule
c. For weeks 16 and 17 no work was accomplished
d. The workforce will have to work extra shifts to finish the project on schedule.

This graph illustrates the progress of a project over a 29-week period, comparing scheduled work with actual work accomplished. The y-axis represents cumulative work, while the x-axis represents time in weeks.

- **Diamond Line (Scheduled Work):** This line shows the planned progress, increasing steadily until it levels off around Week 25.
  
- **Square Line (Actual Work Accomplished):** This line tracks the real progress made. Initially, it lags behind the scheduled work but catches up around Week 19, then continues to track slightly below the scheduled progress.

Throughout the timeline, the graph indicates a consistent effort to follow the planned schedule. However, complete alignment between scheduled and actual work is not achieved until the latter weeks. This visualization highlights the challenges in maintaining project timelines and the adjustments needed to align actual progress with initial plans.
Transcribed Image Text:This graph illustrates the progress of a project over a 29-week period, comparing scheduled work with actual work accomplished. The y-axis represents cumulative work, while the x-axis represents time in weeks. - **Diamond Line (Scheduled Work):** This line shows the planned progress, increasing steadily until it levels off around Week 25. - **Square Line (Actual Work Accomplished):** This line tracks the real progress made. Initially, it lags behind the scheduled work but catches up around Week 19, then continues to track slightly below the scheduled progress. Throughout the timeline, the graph indicates a consistent effort to follow the planned schedule. However, complete alignment between scheduled and actual work is not achieved until the latter weeks. This visualization highlights the challenges in maintaining project timelines and the adjustments needed to align actual progress with initial plans.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 2 images

Blurred answer
Knowledge Booster
Estimating construction costs
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning