Given the Mass Haul Diagram above and the following information: Excavation Cost: $4.00/cu. yd. • Borrow Cost: $4.25/cu. yd. • Overhaul Cost: $1.25/sta*cu. yd. • Free Haul Limit: 600 ft. Compute the total excavation cost: $34,000.00 $10,000.00 $32,000.00 None of these. $26,000.00
Given the Mass Haul Diagram above and the following information: Excavation Cost: $4.00/cu. yd. • Borrow Cost: $4.25/cu. yd. • Overhaul Cost: $1.25/sta*cu. yd. • Free Haul Limit: 600 ft. Compute the total excavation cost: $34,000.00 $10,000.00 $32,000.00 None of these. $26,000.00
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question

Transcribed Image Text:### Mass Diagram and Excavation Cost Computation
**Mass Diagram Description:**
A Mass Diagram is a graphical representation used in civil engineering to show the cumulative volume of earthwork along a linear construction project such as a road or railway. The y-axis represents the Net Cumulative Yardage (in cubic yards), while the x-axis represents the Stations (linear distance along the project).
#### Key Points on the Mass Diagram:
1. **Stations:** These are marked along the x-axis, ranging from 0 to 25.
2. **Net Cumulative Yardage:** This is marked on the y-axis, ranging from -5000 to 5000 cubic yards.
3. **Data Points:** Significant data points along the curve include:
- Station 0: 0 cu.yd
- Station 3: -3000 cu.yd
- Station 6: 1500 cu.yd
- Station 10: 3500 cu.yd
- Station 12: 2100 cu.yd
- Station 15: 1100 cu.yd
- Station 19: 0 cu.yd
- Station 22: 1500 cu.yd
- Station 24: 750 cu.yd
4. **Additional Metrics:**
- Free haul areas are indicated within horizontal green dotted lines, with values labeled such as 5.0, 6.0, 8.0, 7.0, and 6.0.
- Annotations showing various sections with corresponding volumes of earth to be moved are visible, indicating key areas of interest.
### Given Information:
- **Excavation Cost:** $4.00/cu. yd.
- **Borrow Cost:** $4.25/cu. yd.
- **Overhaul Cost:** $1.25/sta*cu. yd.
- **Free Haul Limit:** 600 ft.
**Note**: 1 station = 100 ft
### Computational Task:
Compute the total excavation cost based on the provided data points and the cost parameters.
### Available Multiple-Choice Options:
- $34,000.00
- $10,000.00
- $32,000.00
- None of these
- $26,000.00
To complete the computation, follow these steps:
1. **Determine Quantities:** Assess the volume and direction (cut or fill) at
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 5 steps with 4 images

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education


Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning