Find the critical path method, ea float.
Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter16: Budget Estimating
Section: Chapter Questions
Problem 4RQ: Prepare a typical bay estimate based on the following information: a. Bay size of 350 feet and a...
Related questions
Question
![I.
1. Find the critical path method, earliest start and earliest finish, latest start and latest finish, and slack time or
float.
Activity
Description
Immediate
Duration
Predecessor(s)
A
Select administrative and medical staff.
12
Select site and do site survey.
Select equipment.
Prepare final construction plans and layout.
Bring utilities to the site.
Interview applicants and fill positions in nursing,
support staff, maintenance, and security.
Purchase and take delivery of equipment.
Construct the hospital.
B
9
-
C
A
10
D
10
E
B
24
F
A
10
35
H
40
Develop an information system.
Install the equipment.
Train nurses and support staff.
A
15
E,G,H,
F,I,J
4
K](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F70dbb7b1-7c7d-43c4-b873-ff0072e3c8a1%2Fd619d1fd-1781-4d31-be05-af61581b3d5b%2F553aanf_processed.png&w=3840&q=75)
Transcribed Image Text:I.
1. Find the critical path method, earliest start and earliest finish, latest start and latest finish, and slack time or
float.
Activity
Description
Immediate
Duration
Predecessor(s)
A
Select administrative and medical staff.
12
Select site and do site survey.
Select equipment.
Prepare final construction plans and layout.
Bring utilities to the site.
Interview applicants and fill positions in nursing,
support staff, maintenance, and security.
Purchase and take delivery of equipment.
Construct the hospital.
B
9
-
C
A
10
D
10
E
B
24
F
A
10
35
H
40
Develop an information system.
Install the equipment.
Train nurses and support staff.
A
15
E,G,H,
F,I,J
4
K
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 1 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Fundamentals Of Construction Estimating](https://www.bartleby.com/isbn_cover_images/9781337399395/9781337399395_smallCoverImage.gif)
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
![Fundamentals Of Construction Estimating](https://www.bartleby.com/isbn_cover_images/9781337399395/9781337399395_smallCoverImage.gif)
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,