A state highway department is planning the all road. It estimates that the construction cost (t = 0) will be $200M and maintenance costs will be $IM per year. In addition, every 20 years, a major res will have to be carried out at a cost of $25M. It is estimated that 6 million cars and ucks will use the road cach year, and it is decided that the toll charged to a truc times that of a car. The interest rate is 7%. Determine what the toll should be for each car and truck to cover all expenses for a eriod of 40 years. Assume the toll being charged and the estimated traffic flow

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
III.
A state highway department is planning the construction of a 50 mile, four-lane
toll road. It estimates that the construction cost (t = 0) will be $200M and annual
maintenance costs will be $IM per year. In addition, every 20 years, a major resurfacing
will have to be carried out at a cost of $25M. It is estimated that 6 million cars and 400,000
trucks will use the road cach year, and it is decided that the toll charged to a truck will be
4 times that of a car. The interest rate is 7%.
I
Determine what the toll should be for each car and truck to cover all expenses for a planning
period of 40 years. Assume the toll being charged and the estimated traffic flows do not
vary year-to-year.
Transcribed Image Text:III. A state highway department is planning the construction of a 50 mile, four-lane toll road. It estimates that the construction cost (t = 0) will be $200M and annual maintenance costs will be $IM per year. In addition, every 20 years, a major resurfacing will have to be carried out at a cost of $25M. It is estimated that 6 million cars and 400,000 trucks will use the road cach year, and it is decided that the toll charged to a truck will be 4 times that of a car. The interest rate is 7%. I Determine what the toll should be for each car and truck to cover all expenses for a planning period of 40 years. Assume the toll being charged and the estimated traffic flows do not vary year-to-year.
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Estimating construction costs
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning