Question 1 A Highway contractor has four locations A, B, C, and D on a road contract which crushed stone is to be delivered. The stone, which is all of the same quality is to be supplied from three quarries 1, 2, and 3. The table below shows the relative transportation cost per cubic meter of transporting stone from each quarry to each site. Location Quarry output (m³) Quarry A D Relative transportation costs ($ per m') 1 10 15 11 120 12 8. 6. 3 255 3 10 6. 13 60 45 105 150 135 Quantities required at each location (m³) a) What is the optimal allocation of the crushed stone from each quarry to each location? b) What is the transportation cost corresponding to the solution obtained in part a?

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter11: Pricing Concrete Work
Section: Chapter Questions
Problem 9RQ: Calculate the cost per cubic yard to place concrete using each of the alternatives described. The...
icon
Related questions
icon
Concept explainers
Question

A Highway contractor has four locations A, B, C, and D on a road contract which crushed stone is to be delivered. The stone, which is all of the same quality is to be supplied from three quarries 1, 2, and 3. The table attached shows the relative transportation cost per cubic meter of transporting 
stone from each quarry to each site. 

a) What is the optimal allocation of the crushed stone from each quarry to each location?
b) What is the transportation cost corresponding to the solution obtained in part a?

Question 1
A Highway contractor has four locations A, B, C, and D on a road contract which crushed stone is
to be delivered. The stone, which is all of the same quality is to be supplied from three quarries 1,
2, and 3. The table below shows the relative transportation cost per cubic meter of transporting
stone from each quarry to each site.
Location
Quarry
A
output (m³)
Quarry
В
C
Relative transportation costs ($ per m')
1
9.
10
15
11
120
12
8.
6.
3
255
3
10
6.
13
60
45
105
150
135
Quantities required at each location (m³)
a) What is the optimal allocation of the crushed stone from each quarry to each location?
b) What is the transportation cost corresponding to the solution obtained in part a?
Transcribed Image Text:Question 1 A Highway contractor has four locations A, B, C, and D on a road contract which crushed stone is to be delivered. The stone, which is all of the same quality is to be supplied from three quarries 1, 2, and 3. The table below shows the relative transportation cost per cubic meter of transporting stone from each quarry to each site. Location Quarry A output (m³) Quarry В C Relative transportation costs ($ per m') 1 9. 10 15 11 120 12 8. 6. 3 255 3 10 6. 13 60 45 105 150 135 Quantities required at each location (m³) a) What is the optimal allocation of the crushed stone from each quarry to each location? b) What is the transportation cost corresponding to the solution obtained in part a?
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Pricing concrete work
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,