$B Capacity Be $A Capacity A
Related questions
Question
A 5.55 mtpa LNG plant is being built in Pennsylvania in 2026.
A similar plant built in Louisiana in 2014, with a 7.75 mtpa at a cost of $4.35 billion.
Use an e factor of 0.80
Adjustments are as follows:
The Pennsylvania plant requires $1.2 billion in rock blasting not required in Louisiana.
The Louisiana plant will have an extra LNG tank that won’t be at the Pennsylvania plant that costs $688 millon.
The project expects an escalation of 3.30 from 2014 to 2026.
Do the CFE calculation after the adjustment.