A 5.55 mtpa LNG plant is being built in Pennsylvania in 2026.

A similar plant built in Louisiana in 2014, with a 7.75 mtpa at a cost of $4.35 billion.

Use an e factor of 0.80

Adjustments are as follows:

The Pennsylvania plant requires $1.2 billion in rock blasting not required in Louisiana.

The Louisiana plant will have an extra LNG tank that won’t be at the Pennsylvania plant that costs $688 millon.

The project expects an escalation of 3.30 from 2014 to 2026.

 

Do the CFE calculation after the adjustment.

 

$B
Capacity Be
$A
Capacity A
Transcribed Image Text:$B Capacity Be $A Capacity A
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning