A 5.55 mtpa LNG plant is being built in Pennsylvania in 2026.
A similar plant built in Louisiana in 2014, with a 7.75 mtpa at a cost of $4.35 billion.
Use an e factor of 0.80
Adjustments are as follows:
The Pennsylvania plant requires $1.2 billion in rock blasting not required in Louisiana.
The Louisiana plant will have an extra LNG tank that won’t be at the Pennsylvania plant that costs $688 millon.
The project expects an escalation of 3.30 from 2014 to 2026.
Do the CFE calculation after the adjustment.

Transcribed Image Text:$B
Capacity Be
$A
Capacity A
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps

Recommended textbooks for you


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education


Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning