A 5.55 mtpa LNG plant is being built in Pennsylvania in 2026.

A similar plant built in Louisiana in 2014, with a 7.75 mtpa at a cost of $4.35 billion.

Use an e factor of 0.80

Adjustments are as follows:

The Pennsylvania plant requires $1.2 billion in rock blasting not required in Louisiana.

The Louisiana plant will have an extra LNG tank that won’t be at the Pennsylvania plant that costs $688 millon.

The project expects an escalation of 3.30 from 2014 to 2026.

 

Do the CFE calculation after the adjustment.

 

$B
Capacity Be
$A
Capacity A
Transcribed Image Text:$B Capacity Be $A Capacity A
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer