Question four A new project is to be completed. The following activities need to be completed in the order shown, where times are in weeks. A new project is to be completed. The following activities need to be completed in the order shown, where times are in weeks. Activity Optimistic Most Most Immediate predecessors time Variance likely pessimistic time time AB A 2 3 4 0.11111 2 4 6 0.44444 C A,B 1 2 3 0.11111 D B 1 3 5 0.44444 E A 2 3 4 0.11111 F C 1 4 7 1 G E,F 2 2 2 0 H D,F 2 5 8 1 I G,H 1 3 5 0.44444 J I 2 3 4 0.11111 You must use two decimal places at all times for expected times when they are not integer (you are not permitted to round off to integers). (a) Draw the activity network for this problem (b) Determine the Expected Times. Determine the activity schedule (ES, EF, LS, and LF) as well as slack. Determine and state the critical path for this project. What are the expected time and the variance of the project? (f) What is the probability that the project is completed in 22 or fewer weeks (g) What date should be set such that there is a 94% chance of completion within that time?
Question four A new project is to be completed. The following activities need to be completed in the order shown, where times are in weeks. A new project is to be completed. The following activities need to be completed in the order shown, where times are in weeks. Activity Optimistic Most Most Immediate predecessors time Variance likely pessimistic time time AB A 2 3 4 0.11111 2 4 6 0.44444 C A,B 1 2 3 0.11111 D B 1 3 5 0.44444 E A 2 3 4 0.11111 F C 1 4 7 1 G E,F 2 2 2 0 H D,F 2 5 8 1 I G,H 1 3 5 0.44444 J I 2 3 4 0.11111 You must use two decimal places at all times for expected times when they are not integer (you are not permitted to round off to integers). (a) Draw the activity network for this problem (b) Determine the Expected Times. Determine the activity schedule (ES, EF, LS, and LF) as well as slack. Determine and state the critical path for this project. What are the expected time and the variance of the project? (f) What is the probability that the project is completed in 22 or fewer weeks (g) What date should be set such that there is a 94% chance of completion within that time?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
Related questions
Question

Transcribed Image Text:Question four
A new project is to be completed. The following activities need to be completed in the order shown, where
times are in weeks.
A new project is to be completed. The following activities need to be completed in the order shown, where
times are in weeks.
Activity
Optimistic Most Most
Immediate
predecessors time
Variance
likely pessimistic
time time
AB
A
2
3
4
0.11111
2
4
6
0.44444
C
A,B
1
2
3
0.11111
D
B
1
3
5
0.44444
E
A
2
3
4
0.11111
F
C
1
4
7
1
G
E,F
2
2
2
0
H
D,F
2
5
8
1
I
G,H
1
3
5
0.44444
J
I
2
3
4
0.11111
You must use two decimal places at all times for expected times when they are not integer (you are
not permitted to round off to integers).
(a)
Draw the activity network for this problem
(b)
Determine the Expected Times.
Determine the activity schedule (ES, EF, LS, and LF) as well as slack.
Determine and state the critical path for this project.
What are the expected time and the variance of the project?
(f)
What is the probability that the project is completed in 22 or fewer weeks
(g)
What date should be set such that there is a 94% chance of completion within that time?
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 1 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub