Question four A new project is to be completed. The following activities need to be completed in the order shown, where times are in weeks. A new project is to be completed. The following activities need to be completed in the order shown, where times are in weeks. Activity Optimistic Most Most Immediate predecessors time Variance likely pessimistic time time AB A 2 3 4 0.11111 2 4 6 0.44444 C A,B 1 2 3 0.11111 D B 1 3 5 0.44444 E A 2 3 4 0.11111 F C 1 4 7 1 G E,F 2 2 2 0 H D,F 2 5 8 1 I G,H 1 3 5 0.44444 J I 2 3 4 0.11111 You must use two decimal places at all times for expected times when they are not integer (you are not permitted to round off to integers). (a) Draw the activity network for this problem (b) Determine the Expected Times. Determine the activity schedule (ES, EF, LS, and LF) as well as slack. Determine and state the critical path for this project. What are the expected time and the variance of the project? (f) What is the probability that the project is completed in 22 or fewer weeks (g) What date should be set such that there is a 94% chance of completion within that time?
Question four A new project is to be completed. The following activities need to be completed in the order shown, where times are in weeks. A new project is to be completed. The following activities need to be completed in the order shown, where times are in weeks. Activity Optimistic Most Most Immediate predecessors time Variance likely pessimistic time time AB A 2 3 4 0.11111 2 4 6 0.44444 C A,B 1 2 3 0.11111 D B 1 3 5 0.44444 E A 2 3 4 0.11111 F C 1 4 7 1 G E,F 2 2 2 0 H D,F 2 5 8 1 I G,H 1 3 5 0.44444 J I 2 3 4 0.11111 You must use two decimal places at all times for expected times when they are not integer (you are not permitted to round off to integers). (a) Draw the activity network for this problem (b) Determine the Expected Times. Determine the activity schedule (ES, EF, LS, and LF) as well as slack. Determine and state the critical path for this project. What are the expected time and the variance of the project? (f) What is the probability that the project is completed in 22 or fewer weeks (g) What date should be set such that there is a 94% chance of completion within that time?
Chapter1: Taking Risks And Making Profits Within The Dynamic Business Environment
Section: Chapter Questions
Problem 1CE
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 1 images
Recommended textbooks for you
Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education
Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning
Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education
Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning
Management Information Systems: Managing The Digi…
Management
ISBN:
9780135191798
Author:
Kenneth C. Laudon, Jane P. Laudon
Publisher:
PEARSON
Business Essentials (12th Edition) (What's New in…
Management
ISBN:
9780134728391
Author:
Ronald J. Ebert, Ricky W. Griffin
Publisher:
PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:
9780134237473
Author:
Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:
PEARSON