Draw the Network Diagram, determine the critical path and draw Gantt chart for project scheduling for the following two problems Problem1. Activity Predeccsor Duration(hours) Lag Time(hours) A - 2 0 B A 4 5 C B 3 3 D B 5 0 E D, C 2 0 Problem 2. Activity Predeccsor Duration(months) A - 2 B A 1 C A 3 D B, C 1 E D 2 F D 3 G E 2 H G, F 2
Draw the Network Diagram, determine the critical path and draw Gantt chart for project
Problem1.
Activity Predeccsor Duration(hours) Lag Time(hours)
A - 2 0
B A 4 5
C B 3 3
D B 5 0
E D, C 2 0
Problem 2.
Activity Predeccsor Duration(months)
A - 2
B A 1
C A 3
D B, C 1
E D 2
F D 3
G E 2
H G, F 2
![](/static/compass_v2/shared-icons/check-mark.png)
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)