a) What are the activities on the critical path (using the letters provided) b) What is the shortest amount of time (in days) that this project can finish c) Can activity C be delayed without impacting the end date of the project? yes or no d) If activity C can be delayed, by how many days can it be delayed before the project is delayed? o Craching activi by 1 day will cost ¢100 should vou do this? Why or why pot?
a) What are the activities on the critical path (using the letters provided) b) What is the shortest amount of time (in days) that this project can finish c) Can activity C be delayed without impacting the end date of the project? yes or no d) If activity C can be delayed, by how many days can it be delayed before the project is delayed? o Craching activi by 1 day will cost ¢100 should vou do this? Why or why pot?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:A 4
D 8
Start
B 5
E 3
Finish
Key
C 2
F 2
Activity Duration
Using the network diagram above, answer each of the 5 questions below:
a) What are the activities on the critical path (using the letters provided)
b) What is the shortest amount of time (in days) that this project can finish
c) Can activity C be delayed without impacting the end date of the project? yes or no
d) If activity C can be delayed, by how many days can it be delayed before the project is
delayed?
e) Crashing activity B by 1 day will cost $100, should you do this? Why or why not?
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.