Perform the project crashing for the PROJECT TRES. Details of the project are indicated below. Additional assumptions: •The project overhead cost (POC) per week is PHP 2,000.00 •Total project cost = Total of Normal Cost+ (Project Duration x POC) where: The project duration is in terms of weeks. Express your answers in two decimal places.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

1.) What is the crash cost per week of Activity 5-7?
2.) How much is the least expensive activity?
3.) Based on your critical path, what is the project duration?
State your answer in days assuming 6 days per week.
(Sample answer: 6.00)
4.) What is the total project cost of Project TRES prior to crashing the activities?
Format: PHP 123,456.00]
5.) What is the critical path?
Sample Answer: 1-2-3-4-5-6
6.) Which path has the least total project duration?
Sample Answer: 1-2-3-4-5-6 @ 2 weeks
7.) What is the total difference between the Total Crash Cost and Total Normal Cost?
8.) If activity 2-4 was crashed by one (1) month, what will be the Total Project Cost?
9.) Which activity has the MOST expensive crash cost per week and how much does it cost the project?
The format of your answer must be: Activity 1-2 @ PHP 0,000.00
10.) After performing the project crashing, what is the corresponding time for the optimum cost of the project?
Express your answers in weeks.
Sample: 2 weeks
11.) A penalty for not completing the project beyond (your answer in Question Number 8) weeks is PHP 3,000.00 per week. 
        Expecting that the project will be delayed for additional 2 weeks. 
What will be the new optimum cost of the project?
Format: PHP 000,000.00
12.) TRUE/FALSE.
In Crashing, we start crashing on the MOST EXPENSIVE ACTIVITIES. On the other hand, in relaxing or Uncrashing procedure, the first activity to be relaxed are those which are the LEAST EXPENSIVE ACTIVITIES
13.) Referring to Question Number 9, what is the new corresponding time considering the 2 weeks delay of the project?
Format: 0 weeks
14.) Considering the smooth flow of the construction and no anticipated delay for the project. What will be the total project cost of the project after crashing the activities?
Format of the answer: PHP 00,000.00

Perform the project crashing for the PROJECT TRES.
Details of the project are indicated below.
Additional assumptions:
•The project overhead cost (POC) per week is PHP 2,000.00
•Total project cost = Total of Normal Cost+ (Project Duration x POC)
where:
The project duration is in terms of weeks.
Express your answers in two decimal places.
Solve and finalize the given in a separate paper.
Start by drawing the Network Diagram.
HINT:
POC will be deducted depending on the number of weeks crashed in respective activities.
Total project cost after crashing = Total project cost + crash cost per week - POC per week)
ACTIVITIES
1-2
1-3
2-4
2-5
3-5
4-6
5-6
5-7
6-7
DURATION (WEEKS)
CRASH
4
3
6
1
5
2
2
5
NORMAL
8
5
9
5
7
3
6
9
10
7
INITIAL
COST (PHP)
NORMAL
3,000.00
4,000.00
4,000.00
8,000.00
2,000.00
10,000.00
4,000.00
4,200.00
6,000.00
CRASH
6,000.00
8,000.00
5,500.00
12,000.00
3,200.00
11,200.00
6,800.00
9,000.00
8,700.00
CRASH COST PER
WEEK (PHP)
Transcribed Image Text:Perform the project crashing for the PROJECT TRES. Details of the project are indicated below. Additional assumptions: •The project overhead cost (POC) per week is PHP 2,000.00 •Total project cost = Total of Normal Cost+ (Project Duration x POC) where: The project duration is in terms of weeks. Express your answers in two decimal places. Solve and finalize the given in a separate paper. Start by drawing the Network Diagram. HINT: POC will be deducted depending on the number of weeks crashed in respective activities. Total project cost after crashing = Total project cost + crash cost per week - POC per week) ACTIVITIES 1-2 1-3 2-4 2-5 3-5 4-6 5-6 5-7 6-7 DURATION (WEEKS) CRASH 4 3 6 1 5 2 2 5 NORMAL 8 5 9 5 7 3 6 9 10 7 INITIAL COST (PHP) NORMAL 3,000.00 4,000.00 4,000.00 8,000.00 2,000.00 10,000.00 4,000.00 4,200.00 6,000.00 CRASH 6,000.00 8,000.00 5,500.00 12,000.00 3,200.00 11,200.00 6,800.00 9,000.00 8,700.00 CRASH COST PER WEEK (PHP)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 10 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.