Perform the project crashing for the PROJECT TRES. Details of the project are indicated below. Additional assumptions: •The project overhead cost (POC) per week is PHP 2,000.00 •Total project cost = Total of Normal Cost+ (Project Duration x POC) where: The project duration is in terms of weeks. Express your answers in two decimal places.
1.) What is the crash cost per week of Activity 5-7?
2.) How much is the least expensive activity?
3.) Based on your critical path, what is the project duration?
State your answer in days assuming 6 days per week.
(Sample answer: 6.00)
4.) What is the total project cost of Project TRES prior to crashing the activities?
Format: PHP 123,456.00]
5.) What is the critical path?
Sample Answer: 1-2-3-4-5-6
6.) Which path has the least total project duration?
Sample Answer: 1-2-3-4-5-6 @ 2 weeks
7.) What is the total difference between the Total Crash Cost and Total Normal Cost?
8.) If activity 2-4 was crashed by one (1) month, what will be the Total Project Cost?
9.) Which activity has the MOST expensive crash cost per week and how much does it cost the project?
The format of your answer must be: Activity 1-2 @ PHP 0,000.00
10.) After performing the project crashing, what is the corresponding time for the optimum cost of the project?
Express your answers in weeks.
Sample: 2 weeks
11.) A penalty for not completing the project beyond (your answer in Question Number 8) weeks is PHP 3,000.00 per week.
Expecting that the project will be delayed for additional 2 weeks.
What will be the new optimum cost of the project?
Format: PHP 000,000.00
12.) TRUE/FALSE.
In Crashing, we start crashing on the MOST EXPENSIVE ACTIVITIES. On the other hand, in relaxing or Uncrashing procedure, the first activity to be relaxed are those which are the LEAST EXPENSIVE ACTIVITIES
13.) Referring to Question Number 9, what is the new corresponding time considering the 2 weeks delay of the project?
Format: 0 weeks
14.) Considering the smooth flow of the construction and no anticipated delay for the project. What will be the total project cost of the project after crashing the activities?
Format of the answer: PHP 00,000.00
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 10 images