a) Based on the given information regarding the activities for the project, the project length= 16 weeks. b) The total cost required for completing this project on normal time = $ 12800. c) For reducing the duration of the project by one week, the activity that should be crashed first is activity D The cost of the project based on the first activity selected for crashing will increase by $ 80. weeks. d) The maximum weeks by which the project can be reduced by crashing = 7 Total cost of crashing the project to minimum (or maximum weeks possible) = $1,445".
a) Based on the given information regarding the activities for the project, the project length= 16 weeks. b) The total cost required for completing this project on normal time = $ 12800. c) For reducing the duration of the project by one week, the activity that should be crashed first is activity D The cost of the project based on the first activity selected for crashing will increase by $ 80. weeks. d) The maximum weeks by which the project can be reduced by crashing = 7 Total cost of crashing the project to minimum (or maximum weeks possible) = $1,445".
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Give typed full explanation

Transcribed Image Text:Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table:
a) Based on the given information regarding the activities for the project, the project length = 16 weeks.
b) The total cost required for completing this project on normal time = $ 12800.
c) For reducing the duration of the project by one week, the activity that should be crashed first is activity D
The cost of the project based on the first activity selected for crashing will increase by $ 80.
d) The maximum weeks by which the project can be reduced by crashing = 7 weeks.
Total cost of crashing the project to minimum (or maximum weeks possible) = $1,445.
Normal
Crash
Normal
Activity Time (weeks) Time (weeks) Cost
A
B
с
D
E
F
G
4
2
3
8
6
3
4
3
1
3
4
3
2
2
$2,000
$2,200
$500
$2,400
$800
$3,400
$1,500
Total Cost
with
Crashing Immediate Predecessor(s)
$2,600
$3,000
$500
$2,720
$1,175
$4,800
$1,900
|||| <U
D, E
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 6 steps with 1 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.