Problem 4-5 (Algo) Your project to obtain charitable donations is now 39 days into a planned 49-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 33 days of the project and to bring in $25,400. Even though we are 39 days into the project, we still see that we have only 91% of this activity complete. The second activity relates to company donations and is scheduled to run for 39 days starting on day 6 and extending through day 45. We estimate that, even though we should have (33/39) 84.62% of this activity complete, it is actually only 51% complete. This part of the project was scheduled to bring in $150,400 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,800. So far $176,000 has actually been brought in on the project. Calculate the schedule variance, schedule performance index, cost (actually value in this case) variance, and cost performance index. (Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values. Round your "performance index" values to 3 decimal places.) Schedule variance Schedule performance index Cost variance Cost performance index

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%
Problem 4-5 (Algo)
Your project to obtain charitable donations is now 39 days into a planned 49-day project. The project is divided into 3 activities. The
first activity is designed to solicit individual donations. It is scheduled to run the first 33 days of the project and to bring in $25,400.
Even though we are 39 days into the project, we still see that we have only 91% of this activity complete. The second activity relates to
company donations and is scheduled to run for 39 days starting on day 6 and extending through day 45. We estimate that, even
though we should have (33/39) 84.62% of this activity complete, it is actually only 51% complete. This part of the project was scheduled
to bring in $150,400 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project
and has not started. It is scheduled to bring in an additional $50,800. So far $176,000 has actually been brought in on the project.
Calculate the schedule variance, schedule performance index, cost (actually value in this case) variance, and cost performance index.
(Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values. Round
your "performance index" values to 3 decimal places.)
Schedule variance
Schedule performance index
Cost variance
Cost performance index
Transcribed Image Text:Problem 4-5 (Algo) Your project to obtain charitable donations is now 39 days into a planned 49-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 33 days of the project and to bring in $25,400. Even though we are 39 days into the project, we still see that we have only 91% of this activity complete. The second activity relates to company donations and is scheduled to run for 39 days starting on day 6 and extending through day 45. We estimate that, even though we should have (33/39) 84.62% of this activity complete, it is actually only 51% complete. This part of the project was scheduled to bring in $150,400 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,800. So far $176,000 has actually been brought in on the project. Calculate the schedule variance, schedule performance index, cost (actually value in this case) variance, and cost performance index. (Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values. Round your "performance index" values to 3 decimal places.) Schedule variance Schedule performance index Cost variance Cost performance index
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.