You are in charge of a project. Your team has determined that there are 7 activities to be completed. Here are the activities, the time to complete the activity and the immediate predecessor of the activity. Using this data 1) construct a Gantt Chart, 2) determine the time it will take to complete the project, 3) You are monitoring the progress of this project and discover that activity C is in danger of taking longer than planned due to funding issues. What options do you have to get the project back on track? Activity Time Immediate Predecessor A 10 Weeks None B 6 Weeks A C 7 Weeks A D 6 Weeks B E 8 Weeks C F 3 Weeks D G 4 Weeks F
You are in charge of a project. Your team has determined that there are 7 activities to be completed. Here are the activities, the time to complete the activity and the immediate predecessor of the activity. Using this data 1) construct a Gantt Chart, 2) determine the time it will take to complete the project, 3) You are monitoring the progress of this project and discover that activity C is in danger of taking longer than planned due to funding issues. What options do you have to get the project back on track?
Activity |
Time |
Immediate Predecessor |
A |
10 Weeks |
None |
B |
6 Weeks |
A |
C |
7 Weeks |
A |
D |
6 Weeks |
B |
E |
8 Weeks |
C |
F |
3 Weeks |
D |
G |
4 Weeks |
F |
Find the Given details below:
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 9 images