Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table: D Activity A B C с D E F G a) The expected completion time of the project = a 4 1 7 6 1 1 2 Time (days) m 7 2 7 9 10 4 5 b 8 3 7 13 17 6 9 Immediate Predecessor(s) A A B, C D D Activity H I J K L M N days (round your response to two decimal places). a 3 3 2 8 3 2 7 Time (days) m 3 7 6 9 5 2 8 Immediate b Predecessor(s) 6 9 9 11 7 5 10 E, F G, H I I J K L, M The activities that represent the project's critical path are b) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 53 days or less = places). c) Using the standard normal table, the number of days that would result in 99% probability of completion = days (round your response to two decimal places). (round your response to two decima
Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table:
|
Time (days) |
|
|
|
|
|
Immediate |
|
Time (days) |
|
|
|
|
|
Immediate |
Activity |
a |
|
m |
|
b |
|
Predecessor(s) |
Activity |
a |
|
m |
|
b |
|
Predecessor(s) |
A |
4 |
|
7 |
|
8 |
|
— |
H |
3 |
|
3 |
|
6 |
|
E, F |
B |
1 |
|
2 |
|
3 |
|
— |
I |
3 |
|
7 |
|
9 |
|
G, H |
C |
7 |
|
7 |
|
7 |
|
A |
J |
2 |
|
6 |
|
9 |
|
I |
D |
6 |
|
9 |
|
13 |
|
A |
K |
8 |
|
9 |
|
11 |
|
I |
E |
1 |
|
10 |
|
17 |
|
B, C |
L |
3 |
|
5 |
|
7 |
|
J |
F |
1 |
|
4 |
|
6 |
|
D |
M |
2 |
|
2 |
|
5 |
|
K |
G |
2 |
|
5 |
|
9 |
|
D |
N |
7 |
|
8 |
|
10 |
|
L, M |
Part 2
a) The expected completion time of the project =
enter your response here
days (round your response to two decimal places).
Part 3
The activities that represent the project's critical path are
▼
.
Part 4
b) If the time to complete the activities on the critical path is
53 days or less =
enter your response here
(round your response to two decimal places).
Part 5
c) Using the standard normal table
LOADING...
, the number of days that would result in 99% probability of completion =
enter your response here
days (round your response to two decimal places).