The project contains 6 tasks. We completed three tasks (A, B, C), and started two (D, E) but could not complete them. The planned budget for each task, Actual cost we spent so far, completion rate by today according to the plan, and actual completion rate by today are shown in the table. Actual Cost $80 $150 $100 $130 $90 $0 Task ID A 1) CPI: 2) B C D E F Planned Budget SPI: $100 $150 $100 $160 $200 $100 Planned Completion Rate by Today 100% 100% 100% 25% 50% 0% Actual Completion Rate 100% 100% 100% 50% 6.79 (Round to two decimals/hundredth (xxx)) (Round to two decimals/hundredth (x.xx)) 3) EAC under the assumption that the cost performance will remain as it is (current CPI): (Round to the nearest integer) 50% 0% 4) EAC under the assumption that the cost performance will be as planned (budget rate): (Round to the nearest integer) 5) TCPI:[ (Round to two decimals/hundredth (x.xx))

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The project contains 6 tasks. We completed three tasks (A, B, C), and started two (D, E) but could not complete them.
The planned budget for each task, Actual cost we spent so far, completion rate by today according to the plan, and actual completion
rate by today are shown in the table.
Task ID
Actual Cost
A
8
C
E
F
Planned
Budget
$100
$150
$100
$160
$200
$100
5) TCPI:
$80
$150
$100
$130
$90
$0
Planned
Completion
Rate by Today
100%
100%
100%
25%
50%
0%
Actual
Completion
Rate
100%
100%
100%
50%
50%
0%
1) CPI:
679 (Round to two decimals/hundredth (x.xx))
2) SPI:
(Round to two decimals/hundredth (x.xx))
3) EAC under the assumption that the cost performance will remain as it is (current CPI):
(Round to the nearest integer)
4) EAC under the assumption that the cost performance will be as planned (budget rate):
(Round to the nearest integer)
(Round to two decimals/hundredth (x.xx))
Transcribed Image Text:The project contains 6 tasks. We completed three tasks (A, B, C), and started two (D, E) but could not complete them. The planned budget for each task, Actual cost we spent so far, completion rate by today according to the plan, and actual completion rate by today are shown in the table. Task ID Actual Cost A 8 C E F Planned Budget $100 $150 $100 $160 $200 $100 5) TCPI: $80 $150 $100 $130 $90 $0 Planned Completion Rate by Today 100% 100% 100% 25% 50% 0% Actual Completion Rate 100% 100% 100% 50% 50% 0% 1) CPI: 679 (Round to two decimals/hundredth (x.xx)) 2) SPI: (Round to two decimals/hundredth (x.xx)) 3) EAC under the assumption that the cost performance will remain as it is (current CPI): (Round to the nearest integer) 4) EAC under the assumption that the cost performance will be as planned (budget rate): (Round to the nearest integer) (Round to two decimals/hundredth (x.xx))
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 9 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.