Calculate the schedule variance, schedule performance index, cost (actually value in this case) variance, and cost performance index. (Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values. Round your "performance index" values to 3 decimal places.) Schedule variance Schedule performance index Cost variance Cost performance index $ (50,000) 0.778
Calculate the schedule variance, schedule performance index, cost (actually value in this case) variance, and cost performance index. (Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values. Round your "performance index" values to 3 decimal places.) Schedule variance Schedule performance index Cost variance Cost performance index $ (50,000) 0.778
Chapter1: Taking Risks And Making Profits Within The Dynamic Business Environment
Section: Chapter Questions
Problem 1CE
Related questions
Concept explainers
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Topic Video
Question
![Your project to obtain charitable donations is now 30 days into a planned 40-day project. The
project is divided into 3 activities. The first activity is designed to solicit individual donations. It is
scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30
days into the project, we still see that we have only 90 percent of this activity complete. The
second activity relates to company donations and is scheduled to run for 30 days starting on day 5
and extending through day 35. We estimate that even though we should have approximately 83
percent (or more precisely 25/30) of this activity complete, it is actually only 50 percent complete.
This part of the project was scheduled to bring in $150,000 in donations. The final activity is for
matching funds. This activity is scheduled to run the last 10 days of the project and has not started.
It is scheduled to bring in an additional $50,000. So far $175,000 has actually been brought in on
the project.
Calculate the schedule variance, schedule performance index, cost (actually value in this case)
variance, and cost performance index. (Negative values should be indicated by a minus sign. Do
not round your intermediate calculations or "variance" values. Round your "performance index"
values to 3 decimal places.)
Schedule variance
Schedule performance index
Cost variance
Cost performance index
$
(50,000)
0.778
4](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fdfd56cfb-7bfc-4b10-8703-50c36abb0228%2F2b271ce7-ec49-4ad9-9286-917bf580773c%2Fs8g9549_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Your project to obtain charitable donations is now 30 days into a planned 40-day project. The
project is divided into 3 activities. The first activity is designed to solicit individual donations. It is
scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30
days into the project, we still see that we have only 90 percent of this activity complete. The
second activity relates to company donations and is scheduled to run for 30 days starting on day 5
and extending through day 35. We estimate that even though we should have approximately 83
percent (or more precisely 25/30) of this activity complete, it is actually only 50 percent complete.
This part of the project was scheduled to bring in $150,000 in donations. The final activity is for
matching funds. This activity is scheduled to run the last 10 days of the project and has not started.
It is scheduled to bring in an additional $50,000. So far $175,000 has actually been brought in on
the project.
Calculate the schedule variance, schedule performance index, cost (actually value in this case)
variance, and cost performance index. (Negative values should be indicated by a minus sign. Do
not round your intermediate calculations or "variance" values. Round your "performance index"
values to 3 decimal places.)
Schedule variance
Schedule performance index
Cost variance
Cost performance index
$
(50,000)
0.778
4
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Step 1: Define schedule variance and cost variance
VIEWStep 2: Define schedule performance index and cost performance index
VIEWStep 3: Calculate budgeted review of total Work schedule upto the 30th day of each activity as follows
VIEWStep 4: Calculate budgeted review of total Work Performed upto the 30th day of each activity as follows
VIEWSolution
VIEWTrending now
This is a popular solution!
Step by step
Solved in 5 steps with 14 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Understanding Business](https://www.bartleby.com/isbn_cover_images/9781259929434/9781259929434_smallCoverImage.gif)
Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education
![Management (14th Edition)](https://www.bartleby.com/isbn_cover_images/9780134527604/9780134527604_smallCoverImage.gif)
Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON
![Spreadsheet Modeling & Decision Analysis: A Pract…](https://www.bartleby.com/isbn_cover_images/9781305947412/9781305947412_smallCoverImage.gif)
Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning
![Understanding Business](https://www.bartleby.com/isbn_cover_images/9781259929434/9781259929434_smallCoverImage.gif)
Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education
![Management (14th Edition)](https://www.bartleby.com/isbn_cover_images/9780134527604/9780134527604_smallCoverImage.gif)
Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON
![Spreadsheet Modeling & Decision Analysis: A Pract…](https://www.bartleby.com/isbn_cover_images/9781305947412/9781305947412_smallCoverImage.gif)
Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning
![Management Information Systems: Managing The Digi…](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9780135191798/9780135191798_smallCoverImage.jpg)
Management Information Systems: Managing The Digi…
Management
ISBN:
9780135191798
Author:
Kenneth C. Laudon, Jane P. Laudon
Publisher:
PEARSON
![Business Essentials (12th Edition) (What's New in…](https://www.bartleby.com/isbn_cover_images/9780134728391/9780134728391_smallCoverImage.gif)
Business Essentials (12th Edition) (What's New in…
Management
ISBN:
9780134728391
Author:
Ronald J. Ebert, Ricky W. Griffin
Publisher:
PEARSON
![Fundamentals of Management (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134237473/9780134237473_smallCoverImage.gif)
Fundamentals of Management (10th Edition)
Management
ISBN:
9780134237473
Author:
Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:
PEARSON