Lifang Wu owns an automated machine shop that makes precision auto parts. He has just compiled an input-output report for the grinding work center. Period Planned input Actual input Deviation Planned output Actual output Deviation Initial backlog: 35 For the given information related to "inputs," the values for deviation and total are: 1 90 95 85 85 Period Initial backlog: 35 2 90 95 85 85 The deviation in period 2 = The deviation in period 4 = The total for "planned inputs" = The total for "actual inputs" = The total deviation for "inputs" = For the given information related to "outputs," the values for deviation and total are: The deviation in period 1 = The deviation in period 3 = The total for "planned outputs" The total for "actual outputs" = The total deviation for "outputs" = Fill in the cumulative values for the backlog in each of the periods (given an initial backlog of 35): 3 1 3 95 95 85 80 units (enter your response as an integer, including a minus sign if necessary). units (enter your response as an integer, including a minus sign if necessary). units (enter your response as an integer, including a minus sign if necessary). units (enter your response as an integer, including a minus sign if necessary). units (enter your response as an integer, including a minus sign if necessary). 2 4 95 95 units (enter your response as an integer, including a minus sign if necessary). units (enter your response as an integer, including a minus sign if necessary). units (enter your response as an integer, including a minus sign if necessary). units (enter your response as an integer, including a minus sign if necessary). units (enter your response as an integer, including a minus sign if necessary). = 85 80 4 D Total Total
Lifang Wu owns an automated machine shop that makes precision auto parts. He has just compiled an input
—output report for the grinding work center.
Period |
1 |
2 |
3 |
4 |
Total |
Planned input |
90 |
90 |
95 |
95 |
|
Actual input |
95 |
95 |
95 |
95 |
|
Deviation |
|
|
|
|
|
Planned output |
85 |
85 |
85 |
85 |
|
Actual output |
85 |
85 |
80 |
80 |
|
Deviation |
|
|
|
|
|
Initial backlog:
35 |
|
|
|
|
|
Part 2
For the given information related to "inputs," the values for deviation and total are:
The deviation in period 2 =
enter your response here
units (enter your response as an integer, including a minus sign if necessary).
Part 3
The deviation in period 4 =
enter your response here
units (enter your response as an integer, including a minus sign if necessary).
Part 4
The total for "planned inputs" =
enter your response here
units (enter your response as an integer, including a minus sign if necessary).
Part 5
The total for "actual inputs" =
enter your response here
units (enter your response as an integer, including a minus sign if necessary).
Part 6
The total deviation for "inputs" =
enter your response here
units (enter your response as an integer, including a minus sign if necessary).
Part 7
For the given information related to "outputs," the values for deviation and total are:
The deviation in period 1 =
enter your response here
units (enter your response as an integer, including a minus sign if necessary).
Part 8
The deviation in period 3 =
enter your response here
units (enter your response as an integer, including a minus sign if necessary).
Part 9
The total for "planned outputs" =
enter your response here
units (enter your response as an integer, including a minus sign if necessary).
Part 10
The total for "actual outputs" =
enter your response here
units (enter your response as an integer, including a minus sign if necessary).
Part 11
The total deviation for "outputs" =
enter your response here
units (enter your response as an integer, including a minus sign if necessary).
Part 12
Fill in the cumulative values for the backlog in each of the periods (given an initial backlog of
35):
|
|
|
|
|
|
|
|
|
|
|
|
![**Input-Output Report for Grinding Work Center**
Lifang Wu owns an automated machine shop that makes precision auto parts. He has just compiled an input-output report for the grinding work center.
### Input-Output Table
| Period | 1 | 2 | 3 | 4 | Total |
|-------------------|----|----|----|----|-------|
| **Planned input** | 90 | 90 | 95 | 95 | |
| **Actual input** | 95 | 95 | 95 | 95 | |
| **Deviation** | | | | | |
| **Planned output**| 85 | 85 | 85 | 85 | |
| **Actual output** | 85 | 85 | 80 | 80 | |
| **Deviation** | | | | | |
**Initial backlog: 35**
### Input Deviations and Totals
Based on the given information related to "inputs," calculate the deviations and totals as follows:
- **The deviation in period 2**: _____ units (enter your response as an integer, including a minus sign if necessary).
- **The deviation in period 4**: _____ units (enter your response as an integer, including a minus sign if necessary).
- **The total for "planned inputs"**: _____ units (enter your response as an integer, including a minus sign if necessary).
- **The total for "actual inputs"**: _____ units (enter your response as an integer, including a minus sign if necessary).
- **The total deviation for "inputs"**: _____ units (enter your response as an integer, including a minus sign if necessary).
### Output Deviations and Totals
Given the information related to "outputs," calculate the deviations and totals as follows:
- **The deviation in period 1**: _____ units (enter your response as an integer, including a minus sign if necessary).
- **The deviation in period 3**: _____ units (enter your response as an integer, including a minus sign if necessary).
- **The total for "planned outputs"**: _____ units (enter your response as an integer, including a minus sign if necessary).
- **The total for "actual outputs"**: _____ units (enter your response as an integer, including a minus sign if necessary](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F135ae681-a644-4164-9b10-2ae2e87534da%2F304bce4f-a3e2-465d-9c34-0e150a9b10e7%2Fp6gmt4e_processed.png&w=3840&q=75)
![](/static/compass_v2/shared-icons/check-mark.png)
Step by step
Solved in 3 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)