ACTIVITY WK(S) PRECEDES CRASH COST/WEEK A(START 3 B,C 2 E 4 F 1 F $370 $120 $220 $140 F(END) 3 $400 Suppose that Rafay is only given 8 weeks (instead of 10) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Activity Each Activity Should be Reduced BY (weeks) AO week(s) B1 week(s) C 2 week(s) E O week(s) F Oweek(s) What is the total crashing cost? $ nothing (Enter your response as a whole number.) PLEASE SHOW ME HOW TO GET THE CALUCLATION ON MY OWN SHOW YOUR STEPS I DO KNOW THAT CC-NC/NT-CT BUT I DONT KNOW WHAT FIGURES GOES WHERE AND WHY B C E

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
ACTIVITY WK(S) PRECEDES CRASH COST/WEEK
A(START
$370
$120
$220
1
$140
F(END)
3
$400
Suppose that Rafay is only given 8 weeks (instead of 10) to complete the project. By how many weeks
should each activity be crashed in order to meet the deadline? Assume that you can crash an activity
down to 0 weeks duration.
Activity Each Activity Should be Reduced BY (weeks)
A O week(s)
B1 week(s)
C 2 week(s)
E O week(s)
F Oweek(s)
What is the total crashing cost? $ nothing (Enter your response as a whole number.)
PLEASE SHOW ME HOW TO GET THE CALUCLATION ON MY OWN SHOW YOUR STEPS i DO KNOW
THAT
CC-NC/NT-CT BUT I DONT KNOW WHAT FIGURES GOES WHERE AND WHY
B
с
E
3
2
4
B,C
E
F
F
Transcribed Image Text:ACTIVITY WK(S) PRECEDES CRASH COST/WEEK A(START $370 $120 $220 1 $140 F(END) 3 $400 Suppose that Rafay is only given 8 weeks (instead of 10) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Activity Each Activity Should be Reduced BY (weeks) A O week(s) B1 week(s) C 2 week(s) E O week(s) F Oweek(s) What is the total crashing cost? $ nothing (Enter your response as a whole number.) PLEASE SHOW ME HOW TO GET THE CALUCLATION ON MY OWN SHOW YOUR STEPS i DO KNOW THAT CC-NC/NT-CT BUT I DONT KNOW WHAT FIGURES GOES WHERE AND WHY B с E 3 2 4 B,C E F F
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.