The following represents a project that should be scheduled using CPM:
TIMES (DAYS)
ACTIVITY IMMEDIATE PREDECESSORS
ABCDEFGH
G
H
A
A-D-G-H
A-C-F-H
B-E-G-H
A-D-F-H
A
B
C,D
D, E
F,G
b. What is the critical path?
a
1
1
1
2
3
3
1
2
m
3
2
2
3
4
4
4
4
D53341565
b
11
Transcribed Image Text:The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS ABCDEFGH G H A A-D-G-H A-C-F-H B-E-G-H A-D-F-H A B C,D D, E F,G b. What is the critical path? a 1 1 1 2 3 3 1 2 m 3 2 2 3 4 4 4 4 D53341565 b 11
points
c. What is the expected project completion time?
Note: Do not round intermediate calculations. Round your answer to 2 decimal places.
Project completion time
Answer is complete and correct.
14.66
days
d. What is the probability of completing this project within 16 days?
Note: Use Excel's NORMSDISTO function to find the correct probability for your computed Z-value. Do not round intermediate
calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.
Answer is complete but not entirely correct.
Probability
0.0506
Transcribed Image Text:points c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 2 decimal places. Project completion time Answer is complete and correct. 14.66 days d. What is the probability of completing this project within 16 days? Note: Use Excel's NORMSDISTO function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places. Answer is complete but not entirely correct. Probability 0.0506
Expert Solution
steps

Step by step

Solved in 6 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.