In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: Activity A B C D E F G H Immediate Predecessor(s) Time (days) 3 4 6 6 4 A A B B с D E, F The correct precedence diagram for the project is shown in 4 6 8 Figure 2 Figure 3 G

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
### Project Activity Table and Precedence Diagram Explanation

#### Activity Table
The following table outlines the activities involved in a project at Carl Betterton’s construction company. For each activity, the immediate predecessors and the expected time (in days) required to complete the activity are listed.

| Activity | Immediate Predecessor(s) | Time (days) |
|----------|--------------------------|-------------|
| A        | –                        | 3           |
| B        | A                        | 4           |
| C        | A                        | 6           |
| D        | B                        | 6           |
| E        | B                        | 4           |
| F        | C                        | 4           |
| G        | D                        | 6           |
| H        | E, F                     | 8           |

#### Precedence Diagram Figures

Three figures represent different precedence diagrams for the project. The task is to identify which diagram accurately depicts the precedence relationships outlined in the table.

1. **Figure 1**
   - Activity A leads to activities B and C.
   - Activity B leads to activities D and E.
   - Activity D leads to activity G.
   - Activities E and F converge to lead to activity H.
   
2. **Figure 2**
   - Activity A leads to activities B and C.
   - Activity B leads to activities D and E.
   - Activity C leads to activity F.
   - Activity D leads to activity G.
   - Activities E and F converge to lead to activity H.

3. **Figure 3**
   - Activity A leads to activities B and C.
   - Activity B leads to activities D and E.
   - Activity C leads to activity F.
   - Activity D leads to activity G.
   - Activities E and F converge to lead to activity H.

To determine the correct precedence diagram, consider the immediate predecessors and tasks for each activity as detailed in the activity table. The solution involves matching these details with the diagram's structure.
Transcribed Image Text:### Project Activity Table and Precedence Diagram Explanation #### Activity Table The following table outlines the activities involved in a project at Carl Betterton’s construction company. For each activity, the immediate predecessors and the expected time (in days) required to complete the activity are listed. | Activity | Immediate Predecessor(s) | Time (days) | |----------|--------------------------|-------------| | A | – | 3 | | B | A | 4 | | C | A | 6 | | D | B | 6 | | E | B | 4 | | F | C | 4 | | G | D | 6 | | H | E, F | 8 | #### Precedence Diagram Figures Three figures represent different precedence diagrams for the project. The task is to identify which diagram accurately depicts the precedence relationships outlined in the table. 1. **Figure 1** - Activity A leads to activities B and C. - Activity B leads to activities D and E. - Activity D leads to activity G. - Activities E and F converge to lead to activity H. 2. **Figure 2** - Activity A leads to activities B and C. - Activity B leads to activities D and E. - Activity C leads to activity F. - Activity D leads to activity G. - Activities E and F converge to lead to activity H. 3. **Figure 3** - Activity A leads to activities B and C. - Activity B leads to activities D and E. - Activity C leads to activity F. - Activity D leads to activity G. - Activities E and F converge to lead to activity H. To determine the correct precedence diagram, consider the immediate predecessors and tasks for each activity as detailed in the activity table. The solution involves matching these details with the diagram's structure.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.