The following data represent the plan of a project in Magic Corporation: Times (weeks) Activity A B C D E FGH G I J Predecessor A A A B, C D E, F G a 4 4223 2 1 4 st 1 1 3 1 m 5 4 4 545 m ∞ 3 8 4 2 b 12 12 6 9 5 6 5 9 G H, I a. Draw the network diagram and find the critical path. b. Estimate the expected completion time of the project. c. Calculate the probability that the job will take more than 30 weeks to complete. 11 3

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Problem 1
The following data represent the plan of a project in Magic Corporation:
Times (weeks)
Activity
A
B
C
D
DEF
Predecessor
G
H
1
J
A
A
A
B, C
D
a
4
2
2
1
3
4
1
1
3
1
m
5
4
4545300
E, F
G
G
H, I
a. Draw the network diagram and find the critical path.
b. Estimate the expected completion time of the project.
c. Calculate the probability that the job will take more than 30 weeks to complete.
d. Calculate the probability that the job will take less than 26 weeks.
3
8
b
12
12
6
9
5
6
4
2
5
9
11
3
Сл
Transcribed Image Text:Problem 1 The following data represent the plan of a project in Magic Corporation: Times (weeks) Activity A B C D DEF Predecessor G H 1 J A A A B, C D a 4 2 2 1 3 4 1 1 3 1 m 5 4 4545300 E, F G G H, I a. Draw the network diagram and find the critical path. b. Estimate the expected completion time of the project. c. Calculate the probability that the job will take more than 30 weeks to complete. d. Calculate the probability that the job will take less than 26 weeks. 3 8 b 12 12 6 9 5 6 4 2 5 9 11 3 Сл
Expert Solution
Step 1: a. Find Critical path and b. Find Expected compeltion time of project

 Note:

Since  you  have  posted  a  question  with  multiple  sub  parts,  we  will provide the  solution  only  to the  first  three  sub  parts  as  per our  Q&A guidelines. Please repost the remaining sub parts separately.


Critical path method is project management tool (others e.g WBS, PERT). It uses flow chart of tasks(network /precedence diagram) and helps to find the critical activities of a project in turn help us to find the duration of the project. Project Evaluation and Review Technique-PERT is like CPM but here the activity times are variable (OPTIMISTIC, PESSIMISTIC AND MOST LIKELY). Here we use PERT.

Activity -on -node is a network diagram method that shows the relationship among activities , with each activity being represented on a node

 a.

NETWORK DIAGRAM

 Operations Management homework question answer, step 1, image 1

 


 b

First we find Expected task time of each activity

Expected task time =  (optimistic+4* most likely time+ pessimistic time)/6

Operations Management homework question answer, step 1, image 2


Operations Management homework question answer, step 1, image 3

 


c

PATH durations:

ACEGHJ=     6+4+4+3+7+2=      26

ACEGIJ=       6+4+4+3+5+2=      24

ABEGHJ=     6+5+4+3+7+2=      27

ABEGIJ=       6+5+4+3+5+2=      25

ADFGHJ=     6+5+5+3+7+2=      28

ADFGIJ=       6+5+5+3+5+2=      26

 


 d

Critical path is the one with longest duration. Here ADFGHJ is the critical path.

Duration of the project depends on the duration of critical path.


e.

Expected compeltion time of project= the duration of critical path. = Project completion time= 28 weeks

 

 

trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.