Reliable Garage is completing production of the J2000 kit car. The following data are available for the project: Activity Time (days) 4 4 a. Choose the correct network diagram below for this project. O A. O C. S B 4 S D 11 3 F 2 H F ***g£p. Q FG Activity A B C D E F G H b. Determine the project's critical path and duration. The critical path is A-B-C-D-H and the project duration is 26 day(s). (Enter your response as a whole number.) c. What is the slack for each activity? 2 11 3 2 4 5 Activity А с OB. Activity Time (days) O D. 4 Immediate Predecessor(s) 4 ABCDEFGH + + N = 3245 oooooooo 2 S 11 S Slack (days) 0 0 0 0 0 0 0 ABOOO4L ui А В C C с F D, E, G FC Q FC

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Reliable Garage is completing production of the J2000 kit car. The following data are available for the project:
Activity Time (days)
4
a. Choose the correct network diagram below for this project.
A.
C.
A
4
S
B
4
SH
A
4
E
3
F
2
G
4
D
H
5
F G
Activity
ABCDEFGH
ABCDEFI
с
NA
G
4
H
2
11
3
UAN с
b. Determine the project's critical path and duration.
The critical path is A-B-C-D-H and the project duration is 26 day(s). (Enter your response as a whole number.)
c. What is the slack for each activity?
2
Activity
4
5
Immediate Predecessor(s)
B.
D.
Activity
Time
(days)
4
4
2
11
3
2
4
5
S
A
Slack
(days)
oooooooo
A
B
F
D, E, G
5
F G
Transcribed Image Text:Reliable Garage is completing production of the J2000 kit car. The following data are available for the project: Activity Time (days) 4 a. Choose the correct network diagram below for this project. A. C. A 4 S B 4 SH A 4 E 3 F 2 G 4 D H 5 F G Activity ABCDEFGH ABCDEFI с NA G 4 H 2 11 3 UAN с b. Determine the project's critical path and duration. The critical path is A-B-C-D-H and the project duration is 26 day(s). (Enter your response as a whole number.) c. What is the slack for each activity? 2 Activity 4 5 Immediate Predecessor(s) B. D. Activity Time (days) 4 4 2 11 3 2 4 5 S A Slack (days) oooooooo A B F D, E, G 5 F G
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 2 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.