A new engineering project will be scheduled based on the information given in Table 2. The following activities of the new project are listed with normal time, crash time, and the corresponding costs. Activity Precedent Normal Time Activity A B C D E F G A A B. C D D E, F (weeks) (weeks) 7 6 3 2 4 5 2 Crash Normal Crash Time Cost Cost (RM) (RM) 105,000 120,000 75,000 105,000 135,000 153,000 45,000 67,500 30,000 45,000 60.000 105,000 75.000 120,000 4 5 34 1 2 4 Table 2 Cost Slope (RM/ week) (c) Determine the project duration to complete the project. (A) (B) (C) (D) (E) (G) (Please avoid using any additional formatting characters such as "," or "$" when you fill in blank answers.) (a) Draw a schedule AON network diagram to represent the project. (b) Determine the cost slope for activity "G" in the given table. (G) =
A new engineering project will be scheduled based on the information given in Table 2. The following activities of the new project are listed with normal time, crash time, and the corresponding costs. Activity Precedent Normal Time Activity A B C D E F G A A B. C D D E, F (weeks) (weeks) 7 6 3 2 4 5 2 Crash Normal Crash Time Cost Cost (RM) (RM) 105,000 120,000 75,000 105,000 135,000 153,000 45,000 67,500 30,000 45,000 60.000 105,000 75.000 120,000 4 5 34 1 2 4 Table 2 Cost Slope (RM/ week) (c) Determine the project duration to complete the project. (A) (B) (C) (D) (E) (G) (Please avoid using any additional formatting characters such as "," or "$" when you fill in blank answers.) (a) Draw a schedule AON network diagram to represent the project. (b) Determine the cost slope for activity "G" in the given table. (G) =
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
PLS HELP WITH A,B,C,D,E

Transcribed Image Text:PROJECT PLANNING (CPM) AND COST CRASHING
A new engineering project will be scheduled based on the information given in Table
2. The following activities of the new project are listed with normal time, crash time,
and the corresponding costs.
Activity Precedent
Activity
A
B
C
D
E
F
G
A
A
B. C
D
D
E, F
Normal Crash
Time
Time
(weeks) (weeks)
7
6
2
3
4
5245
5
5
3
4
1
2
4
Table 2
Normal Crash
Cost
Cost
(RM)
(RM)
105,000
120,000
75,000
105.000
135,000 153,000
45,000
67,500
30.000 45,000
60,000
105,000
75,000
120,000
(a) Draw a schedule AON network diagram to represent the project.
(b) Determine the cost slope for activity "G" in the given table.
(G) =
Cost Slope
(RM/ week)
(Please avoid using any additional formatting characters such as "," or
"$" when you fill in blank answers.)
(c) Determine the project duration to complete the project.
(A)
(B)
(C)
(D)
(E)
(G)

Transcribed Image Text:(c) Determine the project duration to complete the project.
The project duration, Te =
(d) Calculate the total cost of the project if there is an indirect cost of RM 6,800 per
week.
Direct cost = RM
Indirect cost = RM
weeks
Total project cost = RM
(e) Determine the activity that should be crashed if you wish to shorten the project
duration by 1 week. Calculate the total project cost after crashing.
Activity to be crashed =
New total project cost after crashing the project duration by 1 week = RM
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step 1: State the given information
VIEWStep 2: a) Draw a schedule AON network diagram
VIEWStep 3: b) Determine the Cost Slope
VIEWStep 4: c) Determine the project duration
VIEWStep 5: d) Calculate Total Cost if Indirect Cost is RM 6800 per week
VIEWStep 6: e) Determine the activity to be crashed first
VIEWSolution
VIEWStep by step
Solved in 7 steps with 15 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.