1. The following are the activities and the time durations towards completion of a project. Compute the most probable or mean time. Indicate your answers in the last column of the table below. (See Table 1) 2. Construct the Network Diagram. Avoid DUMMIES. Determine the Early Start and Early Finish of the project and indicate them in the network. Total Duration of the Project: ______ 3. Re-draw the network diagram below. Determine the Late Start and Late Finish of the project and indicate them in the network. Total Duration of the Project = ____________________   4. Tabulate your results by filling up the cells in the table below. (See Table 2)   5. Determine critical path:___________ 6. Show the critical path by highlighting or tracing it with red-colored lines in the network diagram in item 3.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%

1. The following are the activities and the time durations towards completion of a project. Compute the most probable or mean time. Indicate your answers in the last column of the table below. (See Table 1)

2. Construct the Network Diagram. Avoid DUMMIES. Determine the Early Start and Early Finish of the project and indicate them in the network.

Total Duration of the Project: ______

3. Re-draw the network diagram below. Determine the Late Start and Late Finish of the project and indicate them in the network.
Total Duration of the Project = ____________________

 

4. Tabulate your results by filling up the cells in the table below. (See Table 2)

 

5. Determine critical path:___________

6. Show the critical path by highlighting or tracing it with red-colored lines in the network diagram in item 3.

Activity
A
B
C
D
E
F
G
H
J
K
L
Early Start Early Finish
(ES)
(EF)
Late
Star(LS)
Late Finish
(LF)
Slack
(LS-ES) or
(LF-EF)
Critical
Path
Transcribed Image Text:Activity A B C D E F G H J K L Early Start Early Finish (ES) (EF) Late Star(LS) Late Finish (LF) Slack (LS-ES) or (LF-EF) Critical Path
Activity
A
B
с
D
E
F
G
H
1
J
K
L
a
8
6
3
10
6
9
6
14
10
6
4
1
m
10
7
3
20
7
10
7
15
11
7
7
2
b
12
8
9
30
8
11
8
16
18
8
10
9
Immediate
Predecessor
A
C
B, D, E
B, D, E
F
F
G, H
I, J
G, H
t
(days)
Transcribed Image Text:Activity A B с D E F G H 1 J K L a 8 6 3 10 6 9 6 14 10 6 4 1 m 10 7 3 20 7 10 7 15 11 7 7 2 b 12 8 9 30 8 11 8 16 18 8 10 9 Immediate Predecessor A C B, D, E B, D, E F F G, H I, J G, H t (days)
Expert Solution
steps

Step by step

Solved in 4 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.