1. The following are the activities and the time durations towards completion of a project. Compute the most probable or mean time. Indicate your answers in the last column of the table below. (See Table 1) 2. Construct the Network Diagram. Avoid DUMMIES. Determine the Early Start and Early Finish of the project and indicate them in the network. Total Duration of the Project: ______ 3. Re-draw the network diagram below. Determine the Late Start and Late Finish of the project and indicate them in the network. Total Duration of the Project = ____________________ 4. Tabulate your results by filling up the cells in the table below. (See Table 2) 5. Determine critical path:___________ 6. Show the critical path by highlighting or tracing it with red-colored lines in the network diagram in item 3.
1. The following are the activities and the time durations towards completion of a project. Compute the most probable or mean time. Indicate your answers in the last column of the table below. (See Table 1)
2. Construct the Network Diagram. Avoid DUMMIES. Determine the Early Start and Early Finish of the project and indicate them in the network.
Total Duration of the Project: ______
3. Re-draw the network diagram below. Determine the Late Start and Late Finish of the project and indicate them in the network.
Total Duration of the Project = ____________________
4. Tabulate your results by filling up the cells in the table below. (See Table 2)
5. Determine critical path:___________
6. Show the critical path by highlighting or tracing it with red-colored lines in the network diagram in item 3.