The diagram below was developed for the project launch of Kitty Condo, a new product in the luxury cat cage market. Suppose that you are interested in finding ways to speed up the project at minimal additional cost. Determine the schedule for completing the project in 26 days at minimum cost. Penalty and project overhead costs are negligible. Time and cost data for each activity are shown below. Activity A B C D E F G H 1 Normal Time (days) 9 11 7 11 12 6 10 6 5 Cost ($) Time (days) 1,300 1,050 3,000 2,000 650 700 1,550 600 2,200 Activity A B C D E Crash 7 9 3 10 10 3 7 3 1 Calculate the total cost for this project's schedule. Total cost = $ (Enter your response as a whole number.) Time according to schedule (days) Cost ($) 2,700 1,280 6,200 2,300 1,100 1,900 2,750 1,125 5,800 Activity F - IG T D H A Start B Fill in the table below to show the proper schedule for completing the project in 26 days at minimum cost (i.e., the activity times with crashing for each activity). (Enter your responses as whole numbers.) Diagram E F 3000 Time according to schedule (days) GFinish H Q

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The diagram below was developed for the project launch of Kitty Condo, a new product in the luxury cat cage market. Suppose that you are interested in finding ways to speed
up the project at minimal additional cost. Determine the schedule for completing the project in 26 days at minimum cost. Penalty and project overhead costs are negligible.
Time and cost data for each activity are shown below.
Activity
A B C D E F G I
1
Normal
Time (days)
9
11
7
11
12
6
10
6
5
Cost ($) Time (days)
1,300
1,050
3,000
2,000
650
700
1,550
600
2,200
Activity
A
B
C
D
E
Crash
7
9
3
10
10
3
7
3
1
Calculate the total cost for this project's schedule.
Total cost = $ (Enter your response as a whole number.)
Time according to
schedule (days)
Cost ($)
2,700
1,280
6,200
2,300
1,100
1,900
2,750
1,125
5,800
A
Activity
F
G
H
|
Start B
E
Diagram
Fill in the table below to show the proper schedule for completing the project in 26 days at minimum cost (i.e., the activity times with crashing for each activity). (Enter your
responses as whole numbers.)
F
G
Time according to
schedule (days)
H
Finish
Transcribed Image Text:The diagram below was developed for the project launch of Kitty Condo, a new product in the luxury cat cage market. Suppose that you are interested in finding ways to speed up the project at minimal additional cost. Determine the schedule for completing the project in 26 days at minimum cost. Penalty and project overhead costs are negligible. Time and cost data for each activity are shown below. Activity A B C D E F G I 1 Normal Time (days) 9 11 7 11 12 6 10 6 5 Cost ($) Time (days) 1,300 1,050 3,000 2,000 650 700 1,550 600 2,200 Activity A B C D E Crash 7 9 3 10 10 3 7 3 1 Calculate the total cost for this project's schedule. Total cost = $ (Enter your response as a whole number.) Time according to schedule (days) Cost ($) 2,700 1,280 6,200 2,300 1,100 1,900 2,750 1,125 5,800 A Activity F G H | Start B E Diagram Fill in the table below to show the proper schedule for completing the project in 26 days at minimum cost (i.e., the activity times with crashing for each activity). (Enter your responses as whole numbers.) F G Time according to schedule (days) H Finish
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 7 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.