The Industrial and Systems Engineering Department at Sun University is moving from its old building to a new building. The move must be completed within the 14-day period between semesters. A list of tasks (activities) has been prepared. The activities and precedence requirements are presented in the table below. Three time estimates (in days) are given for each activity: optimistic time, most likely time, and pessimistic time. (a) Perform a forward pass and backward pass through the network to determine the critical path, and the expected duration of the project (b) What completion time should the department specify in its proposal in order to be 85% sure that it will complete the project on time? Activity Activity description Immediate predecessor Optimistic time (days) Most likely time (days) Pessimistic time (days) 1 Initiate move - 0 0 0 2 Prepare new building space 1 2 4 6 3 Pack faculty files and books 1 3 4 5 4 Disconnect computers 1 1 1 2 5 Disconnect lab equipment 1 3 6 9 6 Movers move files and books 2, 3 2 3 6 7 Movers move furniture 4, 6 1 2 3 8 Riggers move lab equipment 5 2 4 6 9 Movers move computers 4 1 1 2 10 Department ready 7, 8, 9 0 0 0 ANSWERS: (a) Critical path(s): ________________, Expected duration of the project_______ (b) ___________________
The Industrial and Systems Engineering Department at Sun University is moving from its old building to a new building. The move must be completed within the 14-day period between semesters. A list of tasks (activities) has been prepared. The activities and precedence requirements are presented in the table below. Three time estimates (in days) are given for each activity: optimistic time, most likely time, and pessimistic time. (a) Perform a forward pass and backward pass through the network to determine the critical path, and the expected duration of the project (b) What completion time should the department specify in its proposal in order to be 85% sure that it will complete the project on time? Activity Activity description Immediate predecessor Optimistic time (days) Most likely time (days) Pessimistic time (days) 1 Initiate move - 0 0 0 2 Prepare new building space 1 2 4 6 3 Pack faculty files and books 1 3 4 5 4 Disconnect computers 1 1 1 2 5 Disconnect lab equipment 1 3 6 9 6 Movers move files and books 2, 3 2 3 6 7 Movers move furniture 4, 6 1 2 3 8 Riggers move lab equipment 5 2 4 6 9 Movers move computers 4 1 1 2 10 Department ready 7, 8, 9 0 0 0 ANSWERS: (a) Critical path(s): ________________, Expected duration of the project_______ (b) ___________________
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
- The Industrial and Systems Engineering Department at Sun University is moving from its old building to a new building. The move must be completed within the 14-day period between semesters. A list of tasks (activities) has been prepared. The activities and precedence requirements are presented in the table below. Three time estimates (in days) are given for each activity: optimistic time, most likely time, and pessimistic time. (a) Perform a forward pass and backward pass through the network to determine the critical path, and the expected duration of the project (b) What completion time should the department specify in its proposal in order to be 85% sure that it will complete the project on time?
Activity |
Activity description |
Immediate predecessor |
Optimistic time (days) |
Most likely time (days) |
Pessimistic time (days) |
1 |
Initiate move |
- |
0 |
0 |
0 |
2 |
Prepare new building space |
1 |
2 |
4 |
6 |
3 |
Pack faculty files and books |
1 |
3 |
4 |
5 |
4 |
Disconnect computers |
1 |
1 |
1 |
2 |
5 |
Disconnect lab equipment |
1 |
3 |
6 |
9 |
6 |
Movers move files and books |
2, 3 |
2 |
3 |
6 |
7 |
Movers move furniture |
4, 6 |
1 |
2 |
3 |
8 |
Riggers move lab equipment |
5 |
2 |
4 |
6 |
9 |
Movers move computers |
4 |
1 |
1 |
2 |
10 |
Department ready |
7, 8, 9 |
0 |
0 |
0 |
ANSWERS: (a) Critical path(s): ________________, Expected duration of the project_______
(b) ___________________
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 11 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.