QUESTION 4 Cashave is responsible for developing a training programme for one major deliverable of the ASP Project. The following table shows the relationships between the activities that must be completed, along with estimates of the durations in days and other relevant information such as Activity Variance, Earliest start and finish times, latest start and finish times. Slack Early Early Late Late Variance Critical (Yes/No) Activity Predecessors Duration Start Finish Start Finish A 4.17 0.00 4.17 0.00 4.17 0.69 B A 6.17 4.17 10.34 4.17 10.34 1.36 C A 2.00 4.17 6.17 8.34 10.34 0.11 D B 4.00 10.34 14.34 11.01 15.01 0.44 E B 3.17 10.34 13.51 11.84 15.01 0.25 F B, C 4.17 10.34 14.51 10.34 14.51 0.25 G B 2.17 10.34 12.51 19.84 22.01 0.25 H F 3.00 14.51 17.51 14.51 17.51 0.11 I F, H 1.50 17.51 19.01 17.51 19.01 0.03 J I 3.00 19.01 22.01 19.01 22.01 0.11 K D, E 7.00 14.34 21.34 15.01 22.01 1.00 You are required to assist Cashave in carrying out the following tasks: i. Complete the project schedule above by inserting the Variance and Slack and indicating the critical activities. ii. Prepare a network diagram based on the information in the table above. 111. Identify the activities, which if delayed, will NOT necessarily delay the entire project. iv. Determine the critical path for this project. V. vi. Determine the expected completion time and variance for the project. Cashave, when asked by Monica, advised her that the time in PART (V) as the longest time the project is likely to take. Comment on the accuracy of the information provided by Cashave to Monica.
QUESTION 4 Cashave is responsible for developing a training programme for one major deliverable of the ASP Project. The following table shows the relationships between the activities that must be completed, along with estimates of the durations in days and other relevant information such as Activity Variance, Earliest start and finish times, latest start and finish times. Slack Early Early Late Late Variance Critical (Yes/No) Activity Predecessors Duration Start Finish Start Finish A 4.17 0.00 4.17 0.00 4.17 0.69 B A 6.17 4.17 10.34 4.17 10.34 1.36 C A 2.00 4.17 6.17 8.34 10.34 0.11 D B 4.00 10.34 14.34 11.01 15.01 0.44 E B 3.17 10.34 13.51 11.84 15.01 0.25 F B, C 4.17 10.34 14.51 10.34 14.51 0.25 G B 2.17 10.34 12.51 19.84 22.01 0.25 H F 3.00 14.51 17.51 14.51 17.51 0.11 I F, H 1.50 17.51 19.01 17.51 19.01 0.03 J I 3.00 19.01 22.01 19.01 22.01 0.11 K D, E 7.00 14.34 21.34 15.01 22.01 1.00 You are required to assist Cashave in carrying out the following tasks: i. Complete the project schedule above by inserting the Variance and Slack and indicating the critical activities. ii. Prepare a network diagram based on the information in the table above. 111. Identify the activities, which if delayed, will NOT necessarily delay the entire project. iv. Determine the critical path for this project. V. vi. Determine the expected completion time and variance for the project. Cashave, when asked by Monica, advised her that the time in PART (V) as the longest time the project is likely to take. Comment on the accuracy of the information provided by Cashave to Monica.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Don't use chatgpt
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 1 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.