Chapter E, Problem 24P
Summary Introduction
To determine: The time taken for the 100th unit.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
If Professor Laurie Macdonald takes 18 minutes to grade the first exam and follows an 75% learning curve then, the amount of time she requires to grade the 25th exam.
The unit time is .263
K
Girish Shambu and Delores Reisel are teammates at a discount store; their new job is assembling bicycles for
customers. Assembly of a bike has a learning rate of 80%. They forgot to time their effort on the first bike, but st
5 hours on the second. They have 6 more bikes to do. Determine approximately how much time will be (was)
required for:
a) The 1st unit = 6.25 hours (round your response to two decimal places).
b) The 8th unit = 3.20 hours (round your response to two decimal places).
c) The total amount of hours to build the 8 units =
hours (round your response to two decimal places).
An effective outcome in performing a task or activity is directly related to the efficiency the performance. true or false?
Chapter E Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Ch. E - Prob. 1DQCh. E - Prob. 2DQCh. E - Prob. 3DQCh. E - Prob. 4DQCh. E - Prob. 5DQCh. E - Prob. 6DQCh. E - Prob. 7DQCh. E - Prob. 8DQCh. E - Prob. 1PCh. E - Prob. 2P
Ch. E - Prob. 3PCh. E - Prob. 4PCh. E - Prob. 5PCh. E - Prob. 6PCh. E - Prob. 7PCh. E - Prob. 8PCh. E - Prob. 9PCh. E - Prob. 10PCh. E - Prob. 11PCh. E - Prob. 12PCh. E - Prob. 13PCh. E - Suad Alwan, the purchasing agent for Dubai...Ch. E - Prob. 15PCh. E - Prob. 16PCh. E - Regional Power owns 25 small power generating...Ch. E - Prob. 18PCh. E - Prob. 19PCh. E - Prob. 20PCh. E - Prob. 21PCh. E - Prob. 22PCh. E - Prob. 23PCh. E - Prob. 24PCh. E - Prob. 25PCh. E - Using the accompanying log-log graph, answer the...Ch. E - Prob. 1CSCh. E - Prob. 2CSCh. E - Prob. 3CS
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The service times for a new data entry clerk have been measured and sequentially recorded as shown below. Report Time (minutes) Report Time (minutes) 1 66 45 2 56 7 44 3 53 8 41 4 48 5 47 The doubling rate based on the given information are: (Round all numerical responses in table below to one decimal place.) Doubling Period 1 to 2 Learning Rate (%) 2 to 4 3 to 6 4 to 8 a) The approximate learning curve rate = % (round your response to the nearest whole number). b) Using an 85% learning curve rate and the above times, the time to complete report number 48 = minutes (round your response to two decimal places).arrow_forwardThe product superx takes 9949 hours for production of 250 unit, where learning curve rate is 99.7% and what will be the total time taken by 2000 units of product superx using cumulative method ?arrow_forward22arrow_forward
- The product adx takes 77 hours for production of 1 unit, where learning curve rate is 57% and what will be the total time taken by 2th unit of product S using incremental unit time method ?arrow_forwardA customer service department has the following resolution response time data: Average Response Time First contact 0.25 hr. Service scheduling 0.50 hr. Wait for service 24.00 hrs. Service 1.50 hrs. Total resolution time 26.25 hrs. What is the value-added ratio (rounded to one decimal place) in this process? a. 8.6% b. 91.4% c. 5.7% d. 28.6%arrow_forwardPlease do not give solution in image format thanku For a production process of 30 units with a learning rate of 85% and a cost of $75 to produce the first unit, construct a table displaying the Cost to Product the Nth Unit and the Cumulative Cost for units 1 through 30.arrow_forward
- If it took 430 hours to produce the first unit of a product, and the learning curve is 90%, how long will it take to produce units 12 through 20? (Do not round intermediate calculations. Round final answer to the nearest integer.) OA. 3,870 OB. 2,545 OC. 3,483 OD. 2,251 OE. 6,281arrow_forward398 not answerarrow_forwardState the limitations of learning curve?arrow_forward
- Girish Shambu and Delores Reisel are teammates at a discount store; their new job is assembling bicycles for customers. Assembly of a bike has a learning rate of 75%. They forgot to time their effort on the first bike, but spent 5 hours on the second. They have 6 more bikes to do. Determine approximately how much time will be (was) required for: a) The 1st unit= hours (round your response to two decimal places). b) The 8th unit-hours (round your response to two decimal places). c) The total amount of hours to build the 8 units-hours (round your response to two decimal places).arrow_forwardElizabeth Perry, a student at SUNY, bought 6 bookcases for her dorm room. Each required unpacking of parts and assembly, which included some nailing and bolting. Elizabeth completed the first bookcase in 5 hours and the second in 4 hours. a) For Elizabeth, the learning rate = % (enter your response as an integerarrow_forwardSolve by Algebra method Wright's methodarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.