Question
Chapter E, Problem 13P
Summary Introduction
To determine: The time taken for the 3rd unit.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Plot and analyze learning curves?
HOW ARE LEARNING CURVES MODELED?
State the Techniques a firm can use to move to a sharper learning curve?
Chapter E Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Ch. E - Prob. 1DQCh. E - Prob. 2DQCh. E - Prob. 3DQCh. E - Prob. 4DQCh. E - Prob. 5DQCh. E - Prob. 6DQCh. E - Prob. 7DQCh. E - Prob. 8DQCh. E - Prob. 1PCh. E - Prob. 2P
Ch. E - Prob. 3PCh. E - Prob. 4PCh. E - Prob. 5PCh. E - Prob. 6PCh. E - Prob. 7PCh. E - Prob. 8PCh. E - Prob. 9PCh. E - Prob. 10PCh. E - Prob. 11PCh. E - Prob. 12PCh. E - Prob. 13PCh. E - Suad Alwan, the purchasing agent for Dubai...Ch. E - Prob. 15PCh. E - Prob. 16PCh. E - Regional Power owns 25 small power generating...Ch. E - Prob. 18PCh. E - Prob. 19PCh. E - Prob. 20PCh. E - Prob. 21PCh. E - Prob. 22PCh. E - Prob. 23PCh. E - Prob. 24PCh. E - Prob. 25PCh. E - Using the accompanying log-log graph, answer the...Ch. E - Prob. 1CSCh. E - Prob. 2CSCh. E - Prob. 3CS
Knowledge Booster
Similar questions
- K At the Dartmouth Assessment Centre, good students have an 85% learning curve and can do a task in 18 minutes after just the eighth time. You would like to weed out the weak students sooner and decide to evaluate them after the third unit. Time required by the good students for the third unit is minutes (round your response to two decimal places) due core icorearrow_forwardLearning Curves The Air Force Museum Foundation has commissioned the purchase of 16 FourF Sixes, pre–World War II aircraft. They will be built completely from scratch to the exact specifications used for the originals. As further authentication, the aircraft will be made using the technologyand manufacturing processes available when the originals were built. Each of the 16 airplanes will beflown to Air Force and aviation museums throughout the country for exhibition. Aviation enthusiastscan also visit the production facility to see exactly how such aircraft were built in 1938.Soren Industries wants to bid on the aircraft contract and asked for and received certain costinformation about the Four F Sixes from the Air Force. The information includes some of the oldcost data from the builders of the original aircraft. The available information is for the total accumulated time as the 1st, 8th, and 32nd aircraft, respectively, were completed. The data reflect a learningrate of 90%.[LO…arrow_forwardExplain how changes in a process will trigger scallops in a learning curve once it's started.arrow_forward
- Predict how human learning will affect task times and cost in the learning curve application of budgeting. Present a scenario and a proposed solution.arrow_forwardYou are asked to do a learning curve analysis as part of your internship project, but you discover that the data is pretty slim. Unfortunately you don't have time to do more field work and you have to come up with the best estimate based on the available data. Here's what you know: It took 98.71 minutes to complete the seventh unit and only 89.35 minutes to complete the twelfth unit. What is your best estimate of the Learning Rate for this process?arrow_forwardHi, I need help solving this OM problem. Thank you!arrow_forward
- You are setting up a new production line for a new type of delivery drones. You observed that the cost for the 10th unit was $6296.33 and the cost for the 80th unit was $4146.15. a) What is the K for the learning curve model of this production line? b) What is the s for the learning curve model of this production line? c) At which unit does its production cost start to be less than $1500?arrow_forwardA new training program at Arid Industries is intended to lower the learning-curve coefficient of a certain molding operation that currently costs $95.50/hour. The current coefficient is .87, and the program hopes to lower the coefficient by 10%. Assume that the time to mold the first product is 8 hours. If the program is successful, what cost savings will be realized when the 2000th piece is produced?arrow_forwardA civil engineering firm designs bridges to span great distances. Years ago, the firm's first design took approximately 1,000 hours to develop. It has subsequently been able to reduce the time, quite dramatically, and believes it is operating on a 70 percent learning curve. Its next bridge design is to span the peaks of Mount Kilimanjaro and will be the 331st bridge it will have designed. How long will it take to design this unique bridge?arrow_forward
- Suppose a manufacturer of copiers has concluded that a 70 percent learning curve applies to the time a new service technician takes to install copy machines. Use the Learning Curve Excel template in MindTap to answer the following questions: a. If the time required to install the first copy machine is estimated to be three hours, what is an estimate of the time required by a new technician to install the third and fourth copiers? Round your answers to one decimal place. For x = 3 it takes hours For x = 4 it takes hours b. If the learning rate changes to 60 or 90 percent, what is an estimate of the time required by a new technician to install the third and fourth copiers? Round your answers to one decimal place. For x = 3 and a 60% LC, it takes For x = 4 and a 60% LC, it takes For x = 3 and a 90% LC, it takes For x = 4 and a 90% LC, it takes hours hours hours hoursarrow_forwardA contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 38 hours. The contractor estimates an 80 percent learning rate. Using POM for Windows or OM Explorer, how long do you estimate the time required to install the sixth pool? The time required to install the sixth pool is enter your response herehours. (Enter your response rounded to two decimal places.) Part 2 What is your estimate of the total time for all six pools? The total time for all six pools is enter your response here hours. (Enter your response rounded to two decimal places.)arrow_forwardA contractor intends to bid on a job installing 30 airport security systems. Because this will be a new line of work for the contractor, he believes there will be a learning effect for the job. After reviewing time records from a similar type of activity, the contractor is convinced that an 85 percent curve is appropriate. He estimates that the first job will take his crew eight days to install. Use the following table for calculation. Learning curve coefficients 70% 75% 80% 85% 90% UnitNumber UnitTime TotalTime UnitTime TotalTime UnitTime TotalTime UnitTime TotalTime UnitTime TotalTime 1 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 2 .700 1.700 .750 1.750 .800 1.800 .850 1.850 .900 1.900 3 .568 2.268 .634 2.384 .702 2.502 .773 2.623 .846 2.746 4 .490 2.758 .562 2.946 .640 3.142 .723 3.345 .810 3.556 5 .437 3.195 .513 3.459 .596 3.738 .686 4.031 .783 4.339 6 .398 3.593 .475 3.934 .562 4.299 .657 4.688 .762 5.101 7 .367 3.960 .446 4.380 .534 4.834…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding Management (MindTap Course List)ManagementISBN:9781305502215Author:Richard L. Daft, Dorothy MarcicPublisher:Cengage Learning
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning