Operations Management: Sustainability and Supply Chain Management (12th Edition)
12th Edition
ISBN: 9780134130422
Author: Jay Heizer, Barry Render, Chuck Munson
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter E, Problem 7P
Summary Introduction
To determine: The time taken for completing all the 7 units.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
K
Manceville Air has just produced the first unit of a large industrial compressor that incorporated new technology in
the control circuits and a new internal venting system. The first unit took 112 hours of labor to manufacture. The
company knows from past experience that this labor content will decrease significantly as more units are produced.
In reviewing past production data, it appears that the company has experienced a 85% learning curve when producing
similar designs. The company is interested in estimating the total time to complete the next 7 units.
Your job as the production cost estimator is to prepare the estimate. Refer to able E.3
Total manufacturing time for the:
first 8 units
Learning Curve Coefficients
Unit Number (N)
8
Unit
Time
.512
80%
Total
Time
5.346
hours
Unit
Time
.614
85%
(round your response to the nearest whole number).
Total
Time
5.936
Unit
Time
729
90%
Total
Time
6.574
X
Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the
second
plane took
18,000
hours to produce. Using an
85%
learning curve and a
$35-per-hour
labor charge, he wants to determine the cost of the
six
additional planes.
Part 2
Time required for the
sixth
unit =
13900
hours (round your response to the nearest whole number).
Part 3
Cost of the
sixth
unit =
486500
dollars (round your response to the nearest whole number).
Part 4
Time required for the
seventh
unit =
enter your response here
hours (round your response to the nearest whole number). Part 5. Cost of the seventh unit?
9. Manufacturer Ċ went through serious process changes in order to eliminate unnecessary
processes from the work flow. However they have to bare the slow down in the process for a
while due to this transition. They want to estimate when they can reach to the expected
performance level based on a 'learning curve' study. For a certain task they have measured a
completion time of 137 minutes in the first time an average employee finished the renewed task.
Please provide the values in the below table for three different learning rates and two different
repetition units.
2nd
4th
13th
27th
Learning Rate
70%
80%
60%
Chapter E Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Ch. E - Prob. 1DQCh. E - Prob. 2DQCh. E - Prob. 3DQCh. E - Prob. 4DQCh. E - Prob. 5DQCh. E - Prob. 6DQCh. E - Prob. 7DQCh. E - Prob. 8DQCh. E - Prob. 1PCh. E - Prob. 2P
Ch. E - Prob. 3PCh. E - Prob. 4PCh. E - Prob. 5PCh. E - Prob. 6PCh. E - Prob. 7PCh. E - Prob. 8PCh. E - Prob. 9PCh. E - Prob. 10PCh. E - Prob. 11PCh. E - Prob. 12PCh. E - Prob. 13PCh. E - Suad Alwan, the purchasing agent for Dubai...Ch. E - Prob. 15PCh. E - Prob. 16PCh. E - Regional Power owns 25 small power generating...Ch. E - Prob. 18PCh. E - Prob. 19PCh. E - Prob. 20PCh. E - Prob. 21PCh. E - Prob. 22PCh. E - Prob. 23PCh. E - Prob. 24PCh. E - Prob. 25PCh. E - Using the accompanying log-log graph, answer the...Ch. E - Prob. 1CSCh. E - Prob. 2CSCh. E - Prob. 3CS
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Hi, I need help solving this OM problem. Thank you!arrow_forwardJericho Vehicles manufacturers special-purpose all terrain vehicles primarily for military and government agencies in Canada as well as for foreign governments. The company is planning to bid on a new all-terrain vehicle specially equipped for desert military action. The company has experienced an 87% learning curve in the past for producing similar vehicles. Based on a prototype model, it estimates the first vehicle produced will require 1,500 hours of direct labour. The order is for 60 all-terrain vehicles. Determine the time that will be required for the 30th and 60th units. Show your calculations to justify your answerarrow_forwardBeth Zion Hospital has received initial certification from the state of California to become a center for liver transplants. The hospital, however, must complete its first 18 transplants under great scrutiny and at no cost to the patients. The very first transplant, just completed, required 28 hours. On the basis of research at the hospital, Beth Zion estimates that it will have an 75% learning curve. Using Table E.3, estimate the time it will take to complete: Unit number 5 75% Unit time: .513 Total time: 3.459 80% Unit number 5 Unit time: .596 Total time: 3.738 85% Unit number 5 Unit time: .686 Total time: 4.031 Unit number 18 75% Unit time: .301 Total time: .8.245 Unit number 18 80% Unit time: 3.94 Total Time: 9.716 Unit number 18 85% Unit time: .508 Total time: 11.405 a) the 5th transplant = 14.36 hours b) the first 5 transplant = ? hours (round your response to two decimal places)arrow_forward
- A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 33 hours. The contractor estimates an 80 percent learning rate. Using POM for Windows or OM Explorer, how long do you estimate the time required to install the fifth pool?arrow_forwardSally suspects strongly that there is a learning curve associated with solving problems assigned for operations management. She notes that it took her approximately 33 minutes to solve the first problem and 17 minutes to solve the fifth problem. (A) Estimate Sally's learning percentage: (B) Using your answer from part A, estimate how long it will take Sally to finish the three remaining problems. Explain and show your answer.arrow_forwardJericho Vehicles manufactures special-purpose all-terrain vehicles primarily for the military and government agencies in the United States and for foreign governments. The company is planning to bid on a new all-terrain vehicle specially equipped for desert military action. The company has experienced an 87% learning curve in the past for producing similar vehicles. Based on a prototype model, it estimates the first vehicle produced will require 1600 hours of direct labor. The order is for 60 all-terrain vehicles. Determine the time that will be required for the 30th and 60th units.arrow_forward
- Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the second plane took 18,000 hours to produce. Using an 85% learning curve and a $35-per-hour labor charge, he wants to determine the cost of the six additional planes. Time required for the sixth unit = hours (round your response to the nearest whole number).arrow_forwardManceville Air has just produced the first unit of a large industrial compressor that incorporated new technology in the control circuits and a new internal venting system. The first unit took 116 hours of labor to manufacture. The company knows from past experience that this labor content will decrease significantly as more units are produced. In reviewing past production data, it appears that the company has experienced a 80% learning curve when producing similar designs. The company is interested in estimating the total time to complete the next 7 units. Your job as the production cost estimator is to prepare the estimate. Refer to table below: 80% 80% 85% Unit Number (N) Unit Time Total Time Unit Time 85% Total Time 90% Unit Time 90% Total Time 8 .512 5.346 .614 5.936 .729 6.574 Total manufacturing time for the= Manufacturing time for the last 7 units (i.e., units 2 thru 8)=arrow_forwardBeth Zion Hospital has received initial certification from the state of California to become a center for liver transplants. The hospital, however, must complete its first 10 transplants under great scrutiny and at no cost to the patients with the hospital picking the expenses. The cost per hour of surgery is estimated to be $4,800. The very first transplant, just completed, required 27 hours. On the basis of research at the hospital, Beth Zion estimates that it will have an 75% learning curve. Using Table E.3, estimate the time it will take to complete: a) the 10th transplant hours (round your response to two decimal places). b) The cost of 10th surgery to Beth Zion Hospital = $ c) the first 10 transplants d) The cost of all 10 surgeries to Beth Zion Hospital = $ whole number). Learning Curve Coefficients Unit Number (N) 10 Unit Time .385 hours (round your response to two decimal places). 75% Total Time 5.589 (round your response to the nearest whole number). Unit Time .477 (round…arrow_forward
- A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 38 hours. The contractor estimates an 80 percent learning rate. Using POM for Windows or OM Explorer, how long do you estimate the time required to install the sixth pool? The time required to install the sixth pool is enter your response herehours. (Enter your response rounded to two decimal places.) Part 2 What is your estimate of the total time for all six pools? The total time for all six pools is enter your response here hours. (Enter your response rounded to two decimal places.)arrow_forwardA) A company working on an 80 percent learning curve has decided that the production standard should be 90 hours the first unit? Show detailed solution i of production for the 128th unit. How much time should be required for B) In a job shop, effective capacity in only 50 percent of design capacity, and actual output is 90 percent of effective of 9 jobs per weeks? Show detailed solution capacity. What design capacity would be needed to achieve an actual output C) You are an engineer who has been assigned a task to perform a HAZOP (Hazard and Operability) study on a Reactor used as main equipment in a certain chemical production plant. i. What are the steps to be followed to perform this study? ii. Use a table to give an example of the parameters, related guide words and deviations that could be used to develop this study.arrow_forwardThe juicer mixer takes 11.5 hours for production of 1 unit, where learning curve rate is 87% and what will be the total time taken by 2th unit of juicer mixer using incremental unit time method ?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.