a)
To determine: The learning rate.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
b)
To determine: The time to complete third book case.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
c)
To determine: The time to complete 4th, 5th, and the 6th book case.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
c)
To determine: The time to complete all 6 cases.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
Want to see the full answer?
Check out a sample textbook solutionChapter E Solutions
Operations Management: Sustainability and Supply Chain Management (12th Edition)
- The first item of a batch took 5 hours to produce. If the learning parameter is 80%, how much time would it take to produce the first seven items.arrow_forwardElizabeth Perry, a student at SUNY, bought 6 bookcases for her dorm room. Each required unpacking of parts and assembly, which included some nailing and bolting. Elizabeth completed the first bookcase in 5 hours and the second in 4 hours. a) For Elizabeth, the learning rate = % (enter your response as an integerarrow_forwardSusan Sherer, an IRS auditor, took 48 minutes to process her first tax return. The IRS uses an 82% learning curve. The amount of processing time that Susan is going to require for the 2nd return __ minutes 4th return __ minutes and 8th return __ minutesarrow_forward
- Girish Shambu and Delores Reisel are teammates at a discount store; their new job is assembling bicycles for customers. Assembly of a bike has a learning rate of 75%. They forgot to time their effort on the first bike, but spent 5 hours on the second. They have 6 more bikes to do. Determine approximately how much time will be (was) required for: a) The 1st unit= hours (round your response to two decimal places). b) The 8th unit-hours (round your response to two decimal places). c) The total amount of hours to build the 8 units-hours (round your response to two decimal places).arrow_forwardSara Bredbenner and Blake DeYoung are teammates at a discount store; their new job is assembling swing sets for customers. Assembly of a swing set has a learning rate of 90%. They forgot to time their effort on the first swing set, but spent 4 hours on the second set. They have 6 more sets to do. Determine approximately how much time will be (was) required for: a) the 1st unit.arrow_forwardGirish Shambu and William Reisel are teammates at a discount store; their new job is assembling bicycles for customers. Assembly of a bike has a learning rate of 70%. They forgot to time their effort on the first bike but spent 4 hours on the second. They have 6 more bikes to do. Determine approximately how much time will be (was) required for: a) The 1st unit = (round your answer to two decimal places)arrow_forward
- Hi, I need help solving this OM problem. Thank you!arrow_forwardSchumacher & Company recently introduced a new ATM system. The Company’s MoneyMatic Division assembles these systems from purchased hardware, using its in-house developed software. It just completed assembling the first batch of 15 units. The last unit (#15) produced required 50 hours of labor, and the learning rate was estimated to be 94 percent for these systems. Another order for 25 units (#16 - #40) of the same system has just arrived. 1) What is the estimated time for the 40th unit? 2) How many total labor hours will be needed to satisfy this second batch (#16 - #40) ? 3) What is the average time to produce this second batch?arrow_forwardThe product superx takes 9949 hours for production of 250 unit, where learning curve rate is 99.7% and what will be the total time taken by 2000 units of product superx using cumulative method ?arrow_forward
- A car production takes 15.2 hours to produce 1 unit of it amwith learning rate 65% find out the total time for 2nd unit with incremental unit timw method ?arrow_forwardK Girish Shambu and Delores Reisel are teammates at a discount store; their new job is assembling bicycles for customers. Assembly of a bike has a learning rate of 80%. They forgot to time their effort on the first bike, but st 5 hours on the second. They have 6 more bikes to do. Determine approximately how much time will be (was) required for: a) The 1st unit = 6.25 hours (round your response to two decimal places). b) The 8th unit = 3.20 hours (round your response to two decimal places). c) The total amount of hours to build the 8 units = hours (round your response to two decimal places).arrow_forwardA teacher wanted to know which learning delivery modes (pure online, pure modular, combination of online and modular) is most effective and has the fastest turnaround time in the submission of accomplished activities among her Grade 12 students. She divided the students into 3 groups, gave them the same activity sheets and asked them to submit as soon as it is completed. She then compared the scores and completion time of the 3 groups. Identify the independent, dependent and extraneous variablearrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.